sjb (05/19/82)
The Columbia was readied today to be towed to the Vehicle Assembly Building, where it will stay for about a week to be mated with an external tank and two SRB's. The movement will have come 48 days after it landed at White Sands after STS-3. In the Orbital Processing Facility, 1,032 tiles were replaced. Ten spots remain to be filled with tiles, seven of them to be filled in the VAB, three at the launch pad. The S-band radios were also fixed along with the toilet. Rollout to the launch pad is now scheduled for 26 May.