I'm helping a friend out with evaluating scheduling packages and I'm looking
for some good test cases:  What I'm looking for is input and the optimal
solution (i.e.)


Activity	Duration	Resources	Preceding Activities
--------------------------------------------------------------------
A1		1     		R1,R2		------
A2		3      		R3		A1
A3		2      		R1,R4		A1
A4		2		R5,R2		A2

etc.

and then, the application figures out the schedule - what I want
is test cases as specified above and the optimal solution.  I'd like a
few easy ones, and a few toughies - i.e. stuff that would require a long
time on a main-frame - but that looks easy.