khayo@sonia.math.ucla.edu (Eric Behr) (06/29/88)
==================================================================== Thursday, June 23, 1988 STS-26 - DISCOVERY (OV 103) - VAB Engineers have resolved the problem with the assist mechanism for opening the nose landing gear doors. A pin in one of the linkages was not aligned properly which prevented the assist mechanism from operating. Closeouts of the nose landing gear are underway and Discovery is scheduled to be lifted vertically by early afternoon. After Discovery has been lifted vertically, it will be another 20 hours before it has been "hard mated" to the external tank and solid rocket boosters. When all the vehicle elements have been connected, the Shuttle Interface Test will be conducted to verify the connections. In addition the functional operation of the solid rocket booster's systems will be verified through various tests. STS-27 - ATLANTIS (0V 104) - OPF BAY 2 Operations planned today include servicing the water coolant loop canisters, verifying the airlock system, preparations to install helium tanks for the main propulsion system, communications testing and installation of the nose cap. Orbiter modifications scheduled today include crew escape, chin panel, improvements to the elevon cove seal, and 17-inch external tank disconnect valves. STS-28 - COLUMBIA (OV 102) - OMRF Powered down operations scheduled today include RTV heat sink, crew escape and improvements to the thermal protection system. STS-27 SOLID ROCKET BOOSTERS - RPSF The rail car cover was removed from the car containing the left aft booster. One of the end rings has been removed and inspections of the gain are underway. Measurements of the j-seal and being taken on the left forward center segment today. ==================================================================== FRIDAY, JUNE 24, 1988 STS-26 - DISCOVERY (OV 103) - VAB Engineers made final adjustments to the limit switch in the nose landing gear door bungee mechanism last night and the gear was stowed for flight at 8 p.m. The switch gives an indication that the bungee is armed and ready to operate and the bungee mechanism assists in opening the nose doors so the gear can be deployed for landing. Discovery was hoisted to the vertical position about 10:30 p.m. last night and is now being mated to the external tank and solid rocket boosters. The "hard mate," when the vehicle elements are bolted together, was scheduled to be completed by this afternoon. The five-day Shuttle Interface Test (SIT) is scheduled to begin Sunday morning. During the test connections between the orbiter, tank, boosters and the mobile launcher platform will be verified. In addition tests the of the solid rocket booster systems will be conducted. Upon successful completion of the SIT tests preparations for rollout to Launch Pad 39-B will begin. Rollout is currently targeted for 12:01 a.m. Friday, July 1. STS-27 - ATLANTIS (0V 104) - OPF BAY 2 Yesterday technicians installed the nose cap and will remove associated support equipment today. Preparations for servicing the ammonia system this weekend are underway. Verification of the orbiter's airlock system is continuing today. Orbiter modifications scheduled include improvements to the elevon cove seal, crew escape and chin panel. STS-28 - COLUMBIA (OV 102) - OMRF Orbiter modifications planned today are crew escape, RTV heat sink, electrical modifications and closeouts for transfer to OPF bay about July 5. STS-27 SOLID ROCKET BOOSTERS - RPSF Inspections of the left aft booster and the left aft center segments are continuing to prepare the segments for stacking in the VAB. Stacking of STS-27 SRB segments is targeted to begin the end of next month. ==================================================================== Monday, June 27, 1988 STS-26 - DISCOVERY (OV 103) - VAB Discovery was "hardmated" or bolted to the external tank early Saturday morning. A few problems were encountered over the weekend such as changing out bolts used in the external tank to orbiter attach yoke and trimming thermal blankets that were interfering with connecting the umbilicals to the orbiter. Today workers will complete hooking up connections between the orbiter and the tank and the mobile launcher platform. The Shuttle Interface Test is scheduled to begin tomorrow which will verify the connections between the orbiter, tank, boosters and the mobile launcher platform. In addition the systems of the solid rocket boosters will be verified. Rollout to Launch Pad 39-B is scheduled for 12:01 a.m. Sunday, July 3. STS-27 - ATLANTIS (0V 104) - OPF BAY 2 This week, one tank set is scheduled to be installed for the lower reactant storage and distribution system and the galley is also scheduled to be installed. Communications testing is approximately 80 percent complete and the target is to be complete by the end of next month. Preparations to service the orbiter's ammonia system are in work. The actual servicing is planned to start in about three weeks. Orbiter modifications are continuing. STS-28 - COLUMBIA (OV 102) - OMRF Closeouts are underway to prepare Columbia for transfer to OPF bay 1 next week. Also the RTV heat sink modification and an electrical modification are underway. STS-27 SOLID ROCKET BOOSTERS - RPSF Preparations are underway to buildup the left aft booster in the Rotation Processing and Surge Facility. ==================================================================== Tuesday, June 28, 1988 STS-26 - DISCOVERY (OV 103) - VAB Preparations for the Shuttle Interface Test (SIT) are underway today. The test is scheduled to begin this afternoon after the monoball connections have been made between the orbiter and tank. During the test, connections between the tank, orbiter, boosters and mobile launcher platform will be verified. In addition, tests will be conducted to verify the systems of the solid rocket boosters. Rollout to Launch Pad 39-B is being assessed based on the actual start of the SIT test. It is currently targeted for 12:01 a.m. Sunday, July 3. STS-27 - ATLANTIS (0V 104) - OPF BAY 2 The main landing gear doors will be closed today to allow access for tile operations. A tank set for the power reactant storage and distribution system is scheduled to be installed this week. Electrical connections of the newly installed auxiliary power unit are planned today. Orbiter modifications are continuing as scheduled. STS-28 - COLUMBIA (OV 102) - OMRF Operations are underway to prepare the orbiter Columbia for transfer to OPF bay 1 next week. Installation of the main landing gear tires is scheduled for Wednesday and Thursday. Actual move of Columbia is planned for 10 a.m. Tuesday, July 5. STS-27 SOLID ROCKET BOOSTERS - RPSF Two stiffeners bands have been installed on the left aft booster as processing continues on the STS-27 solid rocket motor segments. The left aft skirt is scheduled to be delivered this weekend. ==================================================================== Eric