[sci.space.shuttle] Shuttle Status for 6/30/88

yee@ames.arc.nasa.gov (Peter E. Yee) (07/01/88)

Eventually I will get this automated.  I retrieve the updates from an
internal Telemail system.  Normally this is automatic, but right now
I have to hand filter the messages, so there may be a small delay on 
sending them out.
							-Peter
===========================================================================


          KSC SPACE SHUTTLE PROCESSING REPORT FOR - Thursday, June 30, 1988


                        STS-26  -  DISCOVERY (OV 103)  -  VAB

               The Shuttle Interface Test is continuing today to verify
          electrical and mechanical connections between the orbiter
          Discovery, external tank, solid rocket boosters (SRB) and mobile
          launcher platform. Today a hydraulics test of SRB flight controls
          is scheduled to begin.

                The crawler transporter was moved into place in front of
          VAB high bay 3 in preparation for moving the Space Shuttle
          vehicle to the pad. It will be positioned under the launch
          platform in preparation for the pad transfer. Today and tomorrow
          workers are preparing Launch Pad 39-B for the roll out. The
          Rotating Service Structure will be cycled today, and tomorrow the
          flame trench is scheduled to be washed down. In addition, a
          "walkdown" is planned to visually inspect the different levels at
          the pad to ensure its readiness to accept the Space Shuttle
          vehicle.

               It will take about 6-7 hours to transfer Discovery 4.2 miles
          from the VAB to Launch Pad 39-B. The actual time of rollout to
          the launch pad is being assessed as the SIT test progresses. The
          rollout could occur as early as Sunday morning.

                     STS-27  -  ATLANTIS (0V 104)  -  OPF BAY 2

               An oxidizer tank for the power reactant storage and
          distribution system was installed last night and the hydrogen
          tank is scheduled for installation today. Preparations are
          underway to install the orbiter's galley.  Operations continuing
          include: communications testing, orbiter modifications and
          thermal protection system activities.

                        STS-28  -  COLUMBIA (OV 102)  -  OMRF

               The "roll around" tires were installed yesterday as
          preparations to transfer Columbia to OPF bay 1 continue. Workers
          are performing routine maintenance of support equipment in OPF
          bay 1 to support modifications and processing of Columbia. The
          transfer is currently planned for Tuesday, July 5.

                        STS-27 SOLID ROCKET BOOSTERS  -  RPSF

               Processing activities are underway to prepare the segments
          for stacking in the VAB next month. Next week, the left aft skirt
          is scheduled to arrive and aft booster "buildup" operations will
          begin. Buildup activities, which includes mating the skirt and
          aft booster, take about 22 days after which the aft segment will
          be ready for stacking on the mobile launcher platform.

                                      # # # # #





               For more imformation on KSC's Shuttle processing status call
          Lisa Malone at (407) 867-2468.