[sci.space.shuttle] KSC Payload Status for 08/05/88

yee@ames.arc.nasa.gov (Peter E. Yee) (08/05/88)

                                 Payload Status Report
                                 Kennedy Space Center
                                 August 5, 1988


        George Diller


        TDRS-C  (8/88 Discovery)

        PAST MILESTONES:    The  spacecraft  arrived  at   the   Vertical
        Processing  Facility   on May 16.   The associated Inertial Upper
        Stage arrived on May 24.   The TDRS/IUS mechanical mating was ac-
        complished  on  May 31.   The TDRS/White Sands Compatability Test
        was completed on June 8.   TDRS-C/IUS-7 electrical mate  was  ac-
        complished on June 9.  The Interface Verification Test began at 6
        a.m.  on Monday,  June 13 and was completed at 6:00 p.m. on Tues-
        day, June 14.  The Mission Sequence Test was initiated on May 16.
        End to end testing was sucessfuly performed  on  June  21.    The
        final 90 minutes of the Mission Sequence Test was run on June 24.
        Installation  in  the payload canister for a planned dwell period
        was performed July 8.  The payload was removed and  placed  in  a
        test  cell  on July 28 for a planned modification to the IUS air-
        borne  support  equipment,  and  to  install  fresh  bolt  cutter
        ordnance  cartridges  associated  with  deployment  of  the solar
        panels and antennas.


        THIS WEEK:

             The planned modification to the IUS airborne support  equip-
        ment was peformed July 30 without problems.   An additional tilt-
        table overspeed stop was installed to  further  assure  that  the
        IUS/TDRS  cannnot  exceed  its  intended range of travel when the
        payload is rotated from the horizontal position for deployment.

             The operation to replace the bolt cutter ordnance cartridges
        to have the freshest shelf life onboard was performed on July  31
        and also went well.

             The  payload is awaiting the completion of the Flight Readi-
        ness Firing before being returned to the canister.  IUS/TDRS will
        be transported to Pad B five days after FRF.   Once at the launch
        pad  the storable propellants will be loaded aboard,  the payload
        will be installed into the orbiter,  and a final  check  of  both
        TDRS  and  IUS will be performed with the ground control stations
        including White Sands, Sunnyvale,  GSFC,  KSC,  JSC,  and the TRW
        plant.

        TDRS-D  (Discovery 1/89)

             TDRS-D  is  at  the TRW plant in Redondo Beach,  California.
        Final build-up including attachment of  solar  panels,  antennas,
        and external fittings continues.   Shipment from Redondo Beach to
        KSC remains scheduled for October.

        MAGELLAN  (4/89 Atlantis)

             The spacecraft is at the Martin Marietta factory in  Denver,
        Colorado.    Thermal  vacuum  testing  concluded early this week.
        Test results are as expected,  with thermal conditions reaching a
        peak of 2.3 "suns" (2.3 times the energy of the sun) to duplicate
        conditions  expected  during  Magellan's    coast phase to Venus.
        Once at the planet,  the level will be 1.6 suns.   The spacecraft
        is now being removed from the thermal vacuum chamber.

             Next  week  a  6-day  "plugs  out" test will be performed in
        which the spacecraft will run  on  its  own  internal  batteries,
        without external power hook-ups.  Approximately August 20 it will
        undergo  Integrated  Systems  Testing,  checking  out all systems
        simultaneously.   Following this exercise,  the next  major  test
        will occur on September 13, the pre-ship acceptance test.

             The  shipping  of Magellan from Denver to KSC is anticipated
        at some time during the first two weeks of October.