[sci.space.shuttle] Shuttle Status for 08/23/88

yee@ames.arc.nasa.gov (Peter E. Yee) (08/24/88)

            KSC SPACE SHUTTLE PROCESSING REPORT FOR - Tues. Aug. 23, 1988

                     STS-26  -  DISCOVERY (OV 103)  -  PAD 39-B

               Pad 39-B was closed early this morning while the Tracking
          and Data Relay Satellite (TDRS) is being loaded with onboard
          propellant. This operation is scheduled to continue through
          midnight.

               Three other hazardous activities planned this week also
          require the pad to be cleared:

               Tomorrow, the TDRS hydrazine tank is scheduled to be
          pressurized. Thursday, the orbiter's auxiliary power units and
          the solid rocket booster hydraulic power units will be serviced
          with hydrazine for flight.

               Friday ordnance devices will be installed on the Inertial
          Upper Stage. These are small explosive charges that will separate
          the IUS and TDRS about 13 hours after deployment from Discovery's
          payload bay.

                     STS-27  -  ATLANTIS (0V 104)  -  OPF BAY 2

               Technicians are setting up operations in bay 2 for the
          installation of the left orbital maneuvering system pod. The pod
          is currently at the Hypergolic Maintenance Facility being
          prepared for transfer to the OPF. The installation is planned for
          next week. The third main engine is scheduled to be installed
          shortly after the OMS pod. Orbiter systems testing and thermal
          protection system modifications are continuing.

                     STS-28  -  COLUMBIA (OV 102)  -  OPF BAY 1

               Structural inspections and return-to-flight modifications
          are continuing. Thermal protection system operations are
          underway.

                      STS-27 SOLID ROCKET BOOSTERS  -  VAB/RPSF

               The field joint assembly fixture is scheduled to be
          installed today on the right aft center segment in preparation
          for mating to the right aft booster. The right forward center
          segment is scheduled to be transferred from the RPSF to the VAB
          transfer aisle today. Workers are preparing the right forward
          segment in the RPSF.

               Joint closeouts are active on the left booster including
          installing the electrical joint heaters, checking out the heaters
          and installing cork over the joint.