[sci.space.shuttle] Payload Status for 08/26/88

yee@ames.arc.nasa.gov (Peter E. Yee) (08/27/88)

                                 Payload Status Report
                                 Kennedy Space Center
                                 Friday, August 26, 1988


        George Diller


        TDRS-C  (Discovery OV-103)

        PAST MILESTONES:    The  spacecraft  arrived  at   the   Vertical
        Processing  Facility   on May 16.   The associated Inertial Upper
        Stage arrived on May 24.   The TDRS/IUS mechanical mating was ac-
        complished  on  May 31.   The TDRS/White Sands Compatability Test
        was completed on June 8.   TDRS-C/IUS-7 electrical mate  was  ac-
        complished  on June 9.   The Interface Verification Test was com-
        pleted on June 14.  End to end testing was successfully performed
        on June 21.   The Mission Sequence Test was completed on June 24.
        Installation  in the payload canister for a dwell period was per-
        formed July 8.  The payload was removed and placed in a test cell
        on  July 28 for a modification to the IUS airborne support equip-
        ment,  and to replace bolt cutter ordnance cartridges  associated
        with  deployment of the solar panels and antennas.   Changeout of
        the ordnance cartridges was completed July 31.   The payload  was
        transported to the launch pad and placed in the payload changeout
        room on August 15.


        THIS WEEK:

             State  of Health checks for TDRS-C and IUS stand-alone test-
        ing were performed on Aug.  19,  successfully concluded  by  mid-
        night.    These  tests affirmed that the payload test team should
        proceeed with further prelaunch preparations.
	     
             The loading of Hydrazine--the station keeping  and  attitude
        control  propellant aboard the spacecraft--was performed on Tues-
        day, August 23.  The operation,  including initial pressurization
        of the satellite's two fuel tanks with gaseous nitrogen, was com-
        plete  at  10:40 p.m.   The final pressurization was performed on
        Wednesday, Aug. 24.

             On Saturday,  the first set of ordnance is scheduled  to  be
        installed  on the Inertial Upper Stage.   The ordnance is part of
        the mechanism which allows the springs of  the  airborne  support
        equipment  to  release the payload from Discovery.   Safe-and-arm
        ordnance will also be installed on the  first  stage,  to  assure
        that the IUS cannot ignite until planned for ignition.  Other IUS
        ordnance  will  be installed later after the spacecraft is placed
        in the payload bay.   KSC payload and launch  vehicle  management
        have  given  a  "go" for IUS/TDRS installation,  scheduled tenta-
        tively for Monday, Aug. 29.

        TDRS-C/IUS-7 con't


        FORECAST: The Interface Verification Test (IVT) is scheduled  for
        Sep.  2, to check the payload electrical connections with the or-
        biter.  The fimajor test, the "End-to-End" test, is scheduled
        for Sep.  6.   This test assures that ground control stations can
        send  basic  commands  via  the  orbiter  to the IUS and TDRS and
        receive data back about their states of health.    Final  payload
        ordnance operations are scheduled for Sep. 23.



        TDRS-D  (Discovery OV-103)

             TDRS-D  is  at  the TRW plant in Redondo Beach,  California.
        Spacecraft assembly and checkout continues on schedule.  Shipment
        from Redondo Beach to KSC is scheduled for November.




        MAGELLAN  (Atlantis OV-104)

             The spacecraft is at the Martin Marietta factory in  Denver,
        Colorado.

             On Wednesday, Aug. 17, the spacecraft began nine days of In-
        tegrated Systems Testing which is scheduled to be complete today.
        These  tests  check most of Magellan's systems in parallel.   The
        high gain antenna dish has been  undergoing  pattern  testing  at
        Martin  Marietta's  "near field antenna facility" which will con-
        tinue for another week.

             The Magellan radar element was returned to its manufacturer,
        Hughes Aircraft in El Segundo, Ca.,  where its X-band transmitter
        is  being  replaced.   The radar will then be shipped directly to
        KSC.   An engineering radar which has  not been flight  qualified
        is presently installed in the spacecraft.

             The  last  major  test,  the pre-ship acceptance test,  will
        begin on Sep. 7.   Magellan is scheduled to arrive on dock at KSC
        on or about Oct. 7.

             At the Kennedy Space Center,  on Sep.  1, the full NASA-JPL-
        Martin Marietta-McDonnell Douglas test  team  will  meet  at  the
        SAEF-2  spacecraft  checkout facility where Magellan will receive
        final preparations.  The Ground Operations Review for  Magellan's
        SAEF-2  arrival and subsequent spacecraft operations will be held
        at KSC on Sep. 2.