[sci.space.shuttle] STS-26 Release, Part 1

yee@ames.arc.nasa.gov (Peter E. Yee) (09/08/88)

[Due to the large demand, I'm posting the STS-26 Press
 Release (in 4 parts), and the NASA Manifest -PEY]

[There are blanks for artwork in this document -- obviously you'll
 have to use your imaginations and think of what goes in the
 blanks. -PEY]

[The press release is available for anonymous ftp from ames.arc.nasa.gov
 (128.102.18.3).  File is pub/STS-26.  The manifest is pub/Manifest.
 Format is straight ASCII, no compression. -PEY]


special formatting is required for pages 53-58, crew meals.  
Users should format their documents with a left margin of 5,
a line lenght of 110, a text length of 42 and use 12 pitch type.
jsc, ksc, mafc, dfrf, larc & gsfc will receive via pouch mail this
press kit and art read for printing.  Other center will receive printed
copies of the press kit.














RELEASE:  88-121

STS-26 -- THE RETURN TO FLIGHT                    September, 1988

     The Space Shuttle will return to flight when the orbiter 
Discovery is launched on its seventh flight now scheduled for no 
earlier than late September, 1988.

     STS-26 will have as its primary payload the Tracking and 
Data Relay Satellite (TDRS-C) that will complete the 
constellation needed to communicate with spacecraft in low-Earth 
orbit.  TDRS-B was lost in the 51-L Challenger accident.  A third 
TDRS will be launched on a later Shuttle mission to replace the 
first TDRS, which then will be used as an on-orbit spare in the 
event that one of the two operational satellites fails.

     Commander of the five-man crew is Frederick H. (Rick) Hauck, 
captain, USN, a veteran of two Shuttle missions -- 51-A and STS-
7.  Pilot for the mission is Richard O. (Dick) Covey, a colonel 
in the USAF and veteran of the 51-I Shuttle mission.

     Three mission specialists are assigned to the crew:  John M. 
(Mike) Lounge, David C. Hilmers, lt. colonel, USMC, and George D. 
(Pinky) Nelson.  STS-26 will be the second flight for Lounge and 
Hilmers who previously flew on missions 51-I and 51-J, 
respectively.  Nelson has flown two previous Shuttle missions -- 
41-C and 61-C.

     Discovery is scheduled to be launched from the Kennedy Space 
Center, Fla., Launch Pad 39-B, into a 160-nautical-mile, 28.5 
degree orbit.  Liftoff is planned for (TBD) a.m. EDT.  Nominal 
mission duration is 4 days and 1 hour, with landing at Edwards 
Air Force Base, Calif., on Sept. (TBD), 1988, at (TBD) a.m. EDT.

     TDRS-C will be deployed 6 hours, 13 minutes into the mission 
on flight day one.  There are two additional deploy times 
available on that day and one the following day.  The 5,000-pound 
satellite will join the first TDRS, deployed on STS-6 in April 
1983, to provide communications and data links between Earth and 
the Shuttle, as well as other spacecraft.

     TDRS-A is now in geosynchronous orbit (22,300 mi.) over the 
Atlantic Ocean east of Brazil (41 degrees west longitude).  
Following deployment from Discovery, TDRS-C will undergo testing 
and will be moved to its operational position over the Pacific 
Ocean south of Hawaii (171 degrees W. longitude).


                             -more-


                               -2-



     An Air Force-developed inertial upper stage (IUS) will boost 
the TDRS to geosynchronous orbit.  The IUS is mated to the TDRS-C 
and the combination spacecraft and upper stage will be spring 
ejected from the orbiter payload bay.

     Following deployment, Discovery will maneuver to a position 
36 nautical mi. behind and 16 nautical mi. above the TDRS-C/IUS 
before the two-stage motor ignites about 60 minutes after 
deployment.  The three-axis, stabilized upper stage will maneuver 
the TDRS to the desired attitude.  TDRS then will be configured 
for operation by the White Sands Ground Terminal, N.M.

     CONTEL, Atlanta, Ga., owns and operates the TDRS system for 
NASA.  TRW's Defense and Space Systems Group, Redondo Beach, 
Calif., built the satellites.

     The Orbiter Experiments Program Autonomous Supporting 
Instrumentation System (OASIS) will be flown on STS-26 to record 
environmental data in the orbiter payload bay during STS flight 
phases.  OASIS will measure TDRS vibration, strain, acoustics and 
temperature during orbiter ascent, using transducers affixed 
directly to the payload.

     OASIS flight hardware consists of signal conditioning, 
multiplexing and recording equipment mounted on a Shuttle 
adaptive payload carrier behind the TDRS.  Command and status 
interface is achieved through the standard mixed cargo harness 
and the general purpose computers.

     In addition to TDRS-C and OASIS, Discovery will carry 11 
secondary payloads, including two student experiments, involving 
microgravity research, materials processing and electrical storm 
studies.

     After landing at Edwards, Discovery will be towed to the 
NASA Ames-Dryden Flight Research Facility, hoisted atop the 
Shuttle Carrier Aircraft and ferried back to the Kennedy Space 
Center to begin processing for its next flight.


     (END OF GENERAL RELEASE; BACKGROUND INFORMATION FOLLOWS.)















                             -more-


                               -3-



                      GENERAL INFORMATION


NASA Select Television Transmission

     The schedule for television transmissions from the orbiter 
and for the change-of-shift briefings from Johnson Space Center, 
Houston, will be available during the mission at Kennedy Space 
Center, Fla.; Marshall Space Flight Center, Huntsville, Ala.; 
Johnson Space Center; and NASA Headquarters, Washington, D.C.  
The television schedule will be updated daily to reflect changes 
dictated by mission operations.  NASA Select television is 
available on RCA Satcom F-2R, Transponder 13, located at 72 
degrees west longitude.

Special Note to Broadcasters

     Beginning in September and continuing throughout the 
mission, approximately 7 minutes of audio interview material with 
the crew of STS-26 will be available to broadcasters by calling 
202/269-6572.

Status Reports

     Status reports on countdown and mission progress, on-orbit 
activities and landing operations will be produced by the 
appropriate NASA news center.

Briefings

     An STS-26 mission press briefing schedule will be issued 
prior to launch.  During the mission, flight control personnel 
will be on 8-hour shifts.  Change-of-shift briefings by the off-
going flight director will occur at approximately 8-hour 
intervals.





















                             -more-


                               -4-



                      STS-26 -- QUICK LOOK


Crew:  Frederick H. (Rick) Hauck, commander
       Richard O. Covey, pilot
       John M. (Mike) Lounge, mission specialist (MS-1)
       David C. Hilmers, mission specialist (MS-2)
       George D. (Pinky) Nelson, mission specialist (MS-3)

Orbiter:  Discovery (OV-103)

Launch Site:  Pad 39-B, Kennedy Space Center, Fla.

Launch Date/Time:  Late September, 1988, (TBD) a.m. EDT

Launch Window:  3 hours

Orbital Inclination:  28.45 degrees

Altitude:  160 nautical miles

Mission Duration:  4 days, 1 hour

Landing Date/Time:  Sept. (TBD), 1988, (TBD) a.m. EDT

Primary Landing Site:  Edwards AFB, Calif.
  Weather Alternate:  White Sands Space Harbor, N.M.
  Trans-Atlantic Abort:  Ben Guerir, Morocco
  Abort-Once-Around:  Edwards AFB

Primary Payload:  Tracking and Data Relay Satellite (TDRS-C)

Secondary Payloads:
  Automatic Directional Solidification Furnace (ADSF)
  Physical Vapor Transport of Organic Solids (PVTOS)
  Infrared Communications Flight Experiment (IRCFE)
  Protein Crystal Growth Experiment (PCG)
  Isoelectric Focusing Experiment (IEF)
  Phase Partitioning Experiment (PPE)
  Aggregation of Red Blood Cells (ARC)
  Mesoscale Lightning Experiment (MLE)
  Earth-Limb Radiance Experiment (ELRAD)
  2 Shuttle Student Involvement Program (SSIP) Experiments



                   STS-26 MISSION OBJECTIVES

     The primary objective of STS-26 is to deliver NASA's second 
Tracking and Data Relay Satellite to orbit.  The TDRS-C 
deployment will occur 6 hours, 6 minutes into the flight on Orbit 
5.  Day 2 is reserved for backup deployment opportunities.  
Experiments will be activated and performed throughout the 
flight.


                             -more-


                               -5-



           LAUNCH PREPARATIONS, COUNTDOWN AND LIFTOFF

     Discovery was selected as the Space Shuttle for the STS-26 
mission in 1986.  At the time of the 51-L accident, Discovery was 
in temporary storage in the KSC Vehicle Assembly Building (VAB) 
awaiting transfer to the Orbiter Processing Facility (OPF) for 
preparation for the first Shuttle flight from Vandenberg Air 
Force Base, Calif., scheduled for later that year.  Discovery 
last flew in August 1985 on Shuttle mission 51-I, the orbiter's 
sixth flight since it joined the fleet in November 1983.

     In January 1986, the Shuttle Atlantis was in the OPF, 
prepared for the Galileo mission and ready to be mated to the 
boosters and tank in the VAB.  The orbiter Columbia had just 
completed the 61-C mission a few weeks prior to the accident and 
was also in the OPF undergoing post-flight deconfiguration.

     Various Shuttle manifest options were being considered, and 
it was determined that Atlantis would be rolled out to Launch Pad 
39-B for fit checks of new weather protection modifications and 
for an emergency egress exercise and a countdown demonstration 
test.  During that year it also was decided that Columbia would 
be flown to Vandenberg for fit checks.  Discovery was then 
selected for the STS-26 mission.

     Discovery was moved from the VAB High Bay 2, where it was in 
temporary storage, into the OPF the last week of June 1986.  
Power up modifications were active on the orbiter's systems until 
mid-September 1986 when Discovery was transferred to the VAB 
while facility modifications were performed in Bay 1 of the OPF.

     Discovery was moved back into the OPF bay 1 on Oct. 30, 
1987, a milestone that initiated an extensive modification and 
processing flow to ready the vehicle for flight.  The hiatus in 
launching offered an opportunity to "tune-up" and fully check out 
all of the orbiter's systems and treat the orbiter as if it was a 
new vehicle.  Most of the orbiter's major systems and components 
were removed and sent to the respective vendors for modifications 
or to be rebuilt.

     After an extensive powered-down period of 6 months, which 
began in February 1987, Discovery's systems were awakened when 
power surged through its electrical systems on Aug. 3, 1987.

     Discovery remained in the OPF while workers implemented over 
200 modifications and outfitted the payload bay for the Tracking 
and Data Relay Satellite.

     Flight processing began in mid-September during which the 
major components of the vehicle were reinstalled and checked out, 
including the main engines, the right and left hand orbital 
maneuvering system pods and the forward reaction control system.




                             -more-


                               -6-



     In January 1988, Discovery's three main engines arrived at 
KSC and were installed.  Engine 2019 arrived Jan. 6, 1988, and 
was installed in the number one position Jan. 10.  Engine 2022 
arrived Jan. 15 and was installed in the number 2 position Jan. 
24.  Engine 2028 arrived Jan. 21 and was installed in the number 
3 position also on Jan. 24.

     The redesigned solid rocket motor segments began arriving at 
KSC March 1, and the first segment, the left aft booster, was 
stacked on Mobile Launcher 2 in VAB High Bay 3 on March 29. 
Technicians started with the left aft booster and continued 
stacking the four left hand segments before beginning the right 
hand segments on May 5.  The forward assemblies/nose cones were 
attached May 27 and 28.  The SRB field joints were closed out 
prior to mating the external tank to the boosters on June 10.  An 
interface test between the boosters and tank was conducted a few 
days later to verify the connections.

     The OASIS payload was installed in Discovery's payload bay 
on April 19.

     The TDRS arrived at the Vertical Processing Facility on May 
16, and its Inertial Upper Stage (IUS) arrived May 24.  The 
TDRS/IUS mechanical mating was accomplished on May 31.

     Discovery was moved from the OPF to the VAB June 21, where 
it was mated to the external tank and solid rocket boosters.  A 
Shuttle Interface Test was conducted shortly after the mate to 
check out the mechanical and electrial connections between the 
various elements of the Shuttle vehicle and the function of the 
onboard flight systems.

     The assembled Space Shuttle vehicle aboard its mobile 
launcher platform was rolled out of the VAB on July 4, 4.2 miles 
to Launch Pad 39-B for a few major tests and final launch 
preparations.

     A few days after Discovery's orbital manuevering system pods 
were loaded with hypergolic propellants, a tiny leak was detected 
in the left pod (June 14).  Through the use of a small, snake-
like, fiber optics television camera, called a Cobra borescope, 
workers pinpointed the leak to a dynatube fitting in the vent 
line for the reaction control system nitrogen tetroxide storage 
tank, located in the top of the OMS pod.

     The tiny leak was stabilized and controlled by "pulse-
purging" the tank with helium - an inert gas. Pulse-purge is an 
automatic method of maintaining a certain amount of helium in the 
tank. In addition, console operators in the Launch Control Center 
firing room monitored the tank for any change that may have 
required immediate attention.  It was determined that the leak 
would not affect the scheduled Wet Countdown Demonstration Test 
(WCDDT) and the Flight Readiness Firing (FRF) and repair was 
delayed until after these important tests.


                             -more-


                               -7-



     The WCDDT, in which the external tank was loaded with liquid 
oxygen and liquid hydrogen, was conducted August 1.  A few 
problems with ground support equipment resulted in unplanned 
holds during the course of the countdown.

     A leak in the hydrogen umbilical connection at the Shuttle 
tail service mast developed while liquid hydrogen was being 
loaded into the external tank.  Engineers traced the leak to a 
pressure monitoring connector.  During the WCDDT, the leak 
developed again. The test was completed with the liquid hydrogen 
tank partially full and the special tanking tests were deleted.  
Seals in the 8-inch fill line in the tail service mast were 
replaced and leak checked prior to the FRF.

     In addition, the loading pumps in the liquid oxygen storage 
farm were not functioning properly.  The pumps and their 
associated motors were repaired.

     After an aborted first attempt, the 22-second flight 
readiness firing of Discovery's main engines was conducted Aug. 
10.  The first FRF attempt was halted inside the T-10 second mark 
due to a sluggish fuel bleed valve on the number 2 main engine.  
This valve was replaced prior to the FRF.  This firing verified 
that the entire Shuttle system - including launch equipment, 
flight hardware and the launch team - were ready for flight.  
With over 700 pieces of instrumentation installed on the vehicle 
elements and launch pad, the test provided engineers with 
valuable data, including characteristics of the redesigned solid 
rocket boosters.

     After the test, a team of Rockwell technicians began repairs 
to the OMS pod leak.  Four holes were cut into two bulkheads with 
an air powered router on Aug. 17.  A metal "clamshell" device was 
bolted around the leaking dynatube fitting.  The clamshell was 
filled with Furmanite - a dark thick material which consists of 
graphite, silicon and heavy grease and glass fiber.  After an 
initial leak check was successfully performed, covers were bolted 
over the holes Aug. 19, and the tank was pressurized to monitor 
any decay.  No leakage or decay in pressure was noted and the fix 
was deemed a success.

     TDRS-C and its IUS upper stage were transferred from the VPF 
to Launch Pad 39-B on August 15.  The payload was installed into 
Discovery's payload bay August 29.

     A Countdown Demonstration Test, a dress rehearsal for the 
STS-26 flight crew and KSC launch team, is designed as a practice 
countdown for the launch.  At press time, it was planned for 
September 8.







                             -more-


                               -8-



     Launch preparations scheduled the last two weeks prior to 
launch countdown include final vehicle ordnance activities, such 
as power-on stray-voltage checks and resistance checks of firing 
circuits; loading the fuel cell storage tanks; pressurizing the 
hypergolic propellant tanks aboard the vehicle; final payload 
closeouts; and a final functional check of the range safety and 
SRB ignition, safe and arm devices.

     The launch countdown is scheduled to pick up at the T-minus-
43 hour mark, leading up to the first Shuttle liftoff since Jan. 
28, 1986.  The STS-26 launch will be conducted by a joint 
NASA/industry team from Firing Room 1 in the Launch Control 
Center.











































                             -more-


                               -9-



                      MAJOR COUNTDOWN MILESTONES

Count Event             Event

T-43 Hrs                Power up the Space Shuttle

T-34 Hrs                Begin orbiter and ground support 
                        equipment closeouts for launch

T-30 Hrs                Activate Discovery's navigation aids

T-25 Hrs                Load the power reactant storage and 
                        distribution system with liquid oxygen

T-22 Hrs                Load liquid hydrogen into the power 
                        reactant storage and distribution system

T-20 Hrs                Activate and warm up the three inertial 
                        measurement units (IMU)

T-19 Hrs                Perform interface check between Houston-
                        Mission Control and the Merritt Island 
                        Launch Area (MILA) tracking station

T-13 Hrs                Perform pre-ingress switch list in the 
                        flight and middecks

T-11 Hrs                Start 8 hour, 40 minute built-in hold
                        (This time could be adjusted based on day
                        of launch)

T-11 Hrs (counting)     Retract Rotating Service Structure away 
                        from vehicle to launch position

T-9 Hrs                 Activate orbiter's fuel cells

T-8 Hrs                 Configure Mission Control communications 
                        for launch; clear blast danger area

T-7 Hrs                 Perform Eastern Test Range open loop 
                        command test

T-6 Hrs                 Start external tank chilldown and 
                        propellant loading

T-5 Hrs                 Start IMU pre-flight calibration

T-4 Hrs                 Perform MILA antenna alignment

T-3 Hrs                 Begin 2-hour built-in hold; external tank 
                        loading complete; ice team goes to pad 
                        for inspections; wake flight crew (launch 
                        minus 4 hours, 20 minutes)





                             -more-


                              -10-



T-3 Hrs (counting)      Weather briefing; closeout crew has "go" 
                        to proceed to the White Room to begin 
                        preparing Discovery's cockpit for the 
                        flight crew's entry

T-2 Hrs, 30 Min         Flight crew departs O&C Building for 
                        Launch Pad 39-B (launch minus 2 hours, 50 
                        minutes)

T-2 Hrs                 Crew enters orbiter vehicle (launch minus 
                        2 hours, 20 minutes)

T-61 Min                Start pre-flight alignment of IMUs

T-20 Min                Begin 10-minute, built-in hold

T-20 Min (counting)     Configure orbiter computers for launch

T-9 Min                 Begin 10-minute, built-in hold; perform 
                        status check and receive launch director 
                        "go"

T-9 Min (counting)      Start ground launch sequencer

T-7 Min, 30 Sec         Retract orbiter access arm

T-5 Min                 Pilot starts auxiliary power units; arm 
                        range safety, SRB ignition systems

T-3 Min, 30 Sec         Orbiter goes on internal power

T-2 Min, 55 Sec         Pressurize liquid oxygen tank for flight 
                        and retract gaseous oxygen vent hood

T-1 Min, 57 Sec         Pressurize liquid hydrogen tank

T-31 Sec                "Go" from ground computer for orbiter 
                        computers to start the automatic launch 
                        sequence

T-6.6 Sec               "Go" for main engine start

T-3 Sec                 Main engines at 90 percent thrust

T-0                     SRB ignition, holddown post release and 
                        liftoff

T+7 Sec                 Shuttle clears launch tower and control 
                        switches to Johnson Space Center







                             -more-


                              -11-



                   SUMMARY OF MAJOR ACTIVITIES


DAY 1

Ascent
Post-insertion checkout
TDRS-C/IUS deploy
ADSF, PCG, PVTOS, ARC activation



DAY2

Backup TDRS-C/IUS deploy opportunity
PPE



DAY 3

ELRAD
SSIP
Deorbit prep rehearsal



DAY 4

PPE
Flight control systems checkout
Cabin stowage
Landing preparations



DAY 5

Deorbit preparations
Deorbit burn
Landing at EAFB















                             -more-


                              -12-



               STS-26 TRAJECTORY SEQUENCE OF EVENTS


-----------------------------------------------------------------

EVENT                                      MET                INERTIAL
                                        (d:h:m:s)             VELOCITY
                                                                    (fps)
-----------------------------------------------------------------

Launch                                 00:00:00:00

Begin roll maneuver                   00:00:00:07                   1,346

End roll maneuver                     00:00:00:14                   1,418

Begin SSME throttle down to 65%       00:00:00:27                   1,728

Begin SSME throttle up to 104%        00:00:00:59                   2,404

Maximum dynamic pressure (Max Q)      00:00:01:04                   2,551

SRB staging                           00:00:02:04                   5,326

Negative return                       00:00:04:04                   8,275

Main engine cutoff (MECO)*            00:00:08:31                 25,783

Zero thrust                           00:00:08:38                25,871

OMS 2 burn**                           00:00:39:55

TDRS/IUS deploy                        00:06:13:00

Deorbit burn                           03:23:56:00

Landing                                04:00:56:00







 * Apogee, perigee at MECO:  156 x 35 nautical miles
** Direct insertion ascent:  no OMS 1 required
   Apogee, perigee post-OMS 2:  161 x 160 nm









                             -more-


                              -13-



                      SPACE SHUTTLE ABORT MODES

     Space Shuttle launch abort philosophy aims toward safe and 
intact recovery of the flight crew, orbiter and its payload.  
Abort modes include:

     * Abort-to-Orbit (ATO) -- Partial loss of main engine thrust 
       late enough to permit reaching a minimal 105-nautical-mile 
       orbit with orbital maneuvering system engines.

     * Abort-Once-Around (AOA) -- Earlier main engine shutdown 
       with the capability to allow one orbit around before 
       landing at Edwards Air Force Base, Calif.; White Sands 
       Space Harbor, N.M.; or the Shuttle Landing Facility at 
       Kennedy Space Center, Fla.

     * Trans-Atlantic Abort Landing (TAL) -- Loss of two main 
       engines midway through powered flight would force a 
       landing at Ben Guerir, Morocco; Moron, Spain; or Banjul, 
       The Gambia.

     * Return to Launch Site (RTLS) -- Early shutdown of one or 
       more engines and without enough energy to reach Ben 
       Guerir, would result in a pitch around and thrust back 
       towards KSC until within gliding distance of the KSC 
       Shuttle Landing Facility.

     STS-26 contingency landing sites are Edwards AFB, White 
Sands Space Harbor, Kennedy Space Center, Ben Guerir, Moron and 
Banjul.


























                             -more-


                              -14-



              LANDING AND POST-LANDING OPERATIONS

     Kennedy Space Center is responsible for ground operations of 
the orbiter once it has rolled to a stop on the runway at Edwards 
Air Force Base.  Those operations include preparing the Shuttle 
for the return trip to Kennedy.

     After landing, the flight crew aboard Discovery begins 
"safing" vehicle systems.  Immediately after wheel stop, 
specially garbed technicians will determine that any residual 
hazardous vapors around the orbiter are below significant levels, 
before proceeding to other safing operations.

     Once the initial safety assessment is made, access vehicles 
are positioned around the rear of the orbiter so that lines from 
the ground purge and cooling vehicles can be connected to the 
umbilical panels on the aft end of Discovery.

     Freon line connections are completed and coolant begins 
circulating through the umbilicials to aid in heat rejection and 
protect the orbiter's electronic equipment.  Other lines provide 
cooled, humidified air to the payload bay and other cavities to 
remove any residual fumes and provide a safe environment inside 
Discovery.

     A mobile white room is moved around the crew hatch once it 
is verified that there are no concentrations  of toxic gases 
around the forward part of the vehicle.  The crew is expected to 
leave Discovery about 30 to 40 minutes after landing.  As the 
crew exits, technicians enter the orbiter to complete the vehicle 
safing activity.

     A tow tractor will be connected to Discovery to pull it off 
the runway at Edwards and position it inside the Mate/Demate 
Device (MDD) at the nearby Dryden Flight Research Facility.  
After the Shuttle has been jacked and leveled, residual fuel cell 
cryogenics are drained and unused pyrotechnic devices are 
disconnected prior to returning the orbiter to Kennedy.

     The aerodynamic tail cone is installed over the three main 
engines, and the orbiter is bolted on top of the 747 Shuttle 
Carrier Aircraft for the ferry flight back to Florida.  The 747 
is scheduled to leave California about 6 days after landing.  An 
overnight stop is scheduled for refueling and the ferry flight 
continues the next day.

     Once back at Kennedy, Discovery will be pulled inside the 
hangar-like facility for post-flight inspections and in-flight 
anomaly trouble shooting.  These  operations are conducted in 
parallel with the start of routine systems reverification to 
prepare Discovery for its next mission.





                             -more-