[sci.space.shuttle] Payload Status for 09/09/88

yee@ames.arc.nasa.gov (Peter E. Yee) (09/10/88)

                                 Weekly Payload Status Report
                                 NASA Kennedy Space Center
                                 Friday, September 9, 1988


        George Diller


        TDRS-C  (Discovery OV-103)

        PAST MILESTONES:    The  spacecraft  arrived  at   the   Vertical
        Processing  Facility   on May 16.   The associated Inertial Upper
        Stage arrived on May 24.   The TDRS/IUS mechanical mating was ac-
        complished  on  May 31.   The TDRS/White Sands Compatability Test
        was completed on June 8.   TDRS-C/IUS-7 electrical mate  was  ac-
        complished  on June 9.   The Interface Verification Test was com-
        pleted on June 14.  End-to-end testing was successfully performed
        on June 21.   The Mission Sequence Test was completed on June 24.
        Installation  in the payload canister for a dwell period was per-
        formed July 8.  The payload was removed and placed in a test cell
        on  July 28 for a modification to the IUS airborne support equip-
        ment,  and to replace bolt cutter ordnance cartridges  associated
        with  deployment of the solar panels and antennas.   Changeout of
        the ordnance cartridges was completed July 31.   The payload  was
        transported to the launch pad and placed in the payload changeout
        room on Aug. 15.  TDRS state-of-health checks and IUS stand-alone
        testing was performed Aug.  19.   Satellite hydrazine loading was
        accomplished Aug. 23.   Initial ordnance installation for the In-
        tertial Upper Stage occurred Aug.  27.   Installation of IUS/TDRS
        into the payload bay of the orbiter was accomplished Aug. 29.



        THIS WEEK:

             The Interface Verification Test (IVT) for IUS/TDRS began  on
        Saturday,  Sept. 3 at 10:00 p.m. and concluded on Sunday, Sept. 4
        at 9:15 p.m.   Astronauts  Dave  Hilmers  and  Mike  Lounge  par-
        ticipated.  There were no signficant problems.  The test verified
        the payload electrical connections with the orbiter.

             The End-to-End test began at 7:30 a.m.  on Tuesday, Sept. 6,
        concluding at 8:00 p.m.   The exercise encountered no significant
        difficulty.  This test assured that ground control stations could
        send  commands  via  the  orbiter to the IUS and TDRS and receive
        data back about their status.  OASIS was exercised to verify that
        controllers could command the recorder in the payload bay in  the
        same  manner  that  will be performed when Discovery is in space.
        Also,  three  microphones associated with  OASIS  which  are  in-
        stalled on the IUS airborne support equipment were tested.   Also
        Tuesday, the procedure to activate some IUS batteries began.   On
        Wednesday the STS-26 astronauts inspected IUS/TDRS in Discovery's
        payload bay from platforms in the Pad B payload changeout room.

        FORECAST:

            IUS Flight Battery installation is scheduled for Sept. 14-15.

            Final IUS ordnance installation is scheduled for Sept. 23.




        STS-26 MID-DECKS:

             The  Marshall  Space Flight Center mid-deck payloads arrived
        at KSC on Wednesday, Sept. 7,   and were taken to laboratories at
        the  Operations  and  Checkout  Building  where  they  are  being
        prepared for flight.   These payloads are: Automated  Directional
        Solidification  Furnace  (ADSF);  Aggregation  of Red Blood Cells
        (ARC); Protein Crystal Growth (PCG); Isoelectric Focusing (IEF).

             The Johnson Space Center mid-deck payloads will come to  KSC
        pre-packed in the flight mid-deck lockers.  They are scheduled to
        arrive  on  Sept.  13,  and will be taken to the Vehicle Assembly
        Building flight crew systems laboratory.    These  payloads  are:
        Phase  Partitioning  Experiment  (PPE);  Infrared  Communications
        Flight Experiment (IRCFE); Earth Limb Radiance (ELRAD); Mesoscale
        Lightning  Experiment  (MLE);  two  Shuttle  Student  Involvement
        Projects  (SSIP)--The Effect of Weightlessness on Grain Formation
        and Strength in Metals" and "Utilizing A Semi-permeable  Membrane
        to Direct Crystal Growth in Zero Gravity."

             The  PVTOS  (Physical Vapor Transport of Organic Solids) ex-
        periment sponsored by 3M is also scheduled for arrival  on  Sept.
        14.  Pre-launch processing will be performed at the Hangar L life
        sciences facility.


        TDRS-D  (Discovery OV-103)

             TDRS-D  is  at  the TRW plant in Redondo Beach,  California.
        Spacecraft assembly and checkout continues on schedule.  Shipment
        from Redondo Beach to KSC is scheduled for November.


        MAGELLAN  (Atlantis OV-104)

             The spacecraft is at the Martin Marietta factory in  Denver,
        Colorado.

             The  last major test,  the pre-shipment acceptance test,  is
        underway  and  will  conclude  on  Sept.  11.    Afterward,   the
        spacecraft's  weight  and  center  of gravity will be determined.
        The high gain antenna dish is at the Near Field Antenna  Facility
        undergoing a final overall test.

             The Magellan radar element was returned to its manufacturer,
        Hughes Aircraft in El Segundo,  Ca., where its X-band transmitter
        is being replaced.   The radar will then be shipped  directly  to
        KSC,  shortly  after  spacecraft  arrival.   An engineering radar
        which has  not been flight qualified is  presently  installed  in
        the spacecraft.   Also, an onboard radio transponder used to com-
        municate with the ground has been returned to Motorola for repair
        and will be shipped directly to KSC.

             Magellan is scheduled to arrive at KSC on Oct. 7.