[sci.space.shuttle] Shuttle Status for 09/15/88

yee@ames.arc.nasa.gov (Peter E. Yee) (09/16/88)

           KSC SPACE SHUTTLE PROCESSING REPORT FOR - Thurs. Sept. 15, 1988

                     STS-26  -  DISCOVERY (OV 103)  -  PAD 39-B

               Troubleshooting efforts revealed two very small internal
          leaks in the liquid hydrogen portion of the main propulsion
          system. When two valves were cycled, the pressure decay rates
          returned to within the specifications. The data is currently
          being analyzed, but it appears that the problem has been found
          and corrected. The valves involved, the outboard fill and drain
          and the return-to-launch-site dump valves, are operated
          hydraulically.

               Preparations for the helium signature leak test of the main
          propulsion system and the main engines are in work. The test is
          scheduled to begin this afternoon and is designed to reveal any
          leaks in the system. Post-Flight Readiness Firing (FRF) tests of
          the liquid oxygen system are underway today.

               Batteries have been installed on the Inertial Upper Stage
          and a pre-flight test is scheduled to begin at 3 p.m. today. The
          test simulates events that occur with the IUS during the last
          hours of the launch countdown.

               Testing of the newly installed poppets for the gasous oxygen
          flow control valves was completed.

               Yesterday, Shuttle managers concluded the Flight Readiness
          Review and decided the program is ready for the STS-26 launch
          later this month. A decision on the exact launch date will not be
          announced any earlier than tomorrow. Managers wanted to evaluate
          the effects of Hurricane Gilbert which is headed for the Texas
          coastline and wanted more information on the small leak in
          Discovery's liquid hydrogen system.

                     STS-27  -  ATLANTIS (0V 104)  -  OPF BAY 2

               Preparations are underway to install the third main engine
          tomorrow. Other activities scheduled today include: main
          propulsion system leak checks, thermal protection system
          operations, midbody closeouts, pressure measurements of the
          installed flight tires, and installation of flight tires on the
          main gear. Preparations will begin today to remove and replace an
          actuator on the right hand orbital maneuvering system pod. The
          suspect actuator was discovered during interface testing.

                     STS-28  -  COLUMBIA (OV 102)  -  OPF BAY 1

               Installation of electronic components is underway today to
          support next week's planned power up. Today, workers are
          servicing the orbiter's water coolant loop and implementing
          return-to-flight modifications and inspections.


                        STS-27 SOLID ROCKET BOOSTERS  -  VAB

               Closeouts of the field joints on the right hand solid rocket
          booster are underway today. The external tank for the STS-27
          vehicle is scheduled to be mated to the boosters next week.

               At the Rotation Processing and Surge Facility, technicians
          are processing segments for the STS-29 booster stack.