[sci.space.shuttle] Payload Status 10/08/88

yee@ames.arc.nasa.gov (Peter E. Yee) (10/09/88)

                                 Weekly Payload Status Report
                                 NASA Kennedy Space Center
                                 Saturday, October 8, 1988


        George Diller


        TDRS-C  (Discovery OV-103)

        PAST MILESTONES:    The  spacecraft  arrived  at   the   Vertical
        Processing  Facility   on May 16.   The associated Inertial Upper
        Stage arrived on May 24.   The TDRS/IUS mechanical mating was ac-
        complished  on  May 31.   The TDRS/White Sands Compatibility Test
        was completed on June 8.   TDRS-C/IUS-7 electrical mate  was  ac-
        complished  on June 9.   The Interface Verification Test was com-
        pleted on June 14.  End-to-end testing was successfully performed
        on June 21.   The Mission Sequence Test was completed on June 24.
        Installation  in the payload canister for a dwell period was per-
        formed July 8.  The payload was removed and placed in a test cell
        on  July 28 for a modification to the IUS airborne support equip-
        ment,  and to replace bolt cutter ordnance cartridges  associated
        with  deployment of the solar panels and antennas.   Changeout of
        the ordnance cartridges was completed July 31.   The payload  was
        transported to the launch pad and placed in the payload changeout
        room on Aug. 15.  TDRS state-of-health checks and IUS stand-alone
        testing was performed Aug.  19.   Satellite hydrazine loading was
        accomplished Aug. 23.   Initial ordnance installation for the In-
        tertial Upper Stage occurred Aug.  26.   Installation of IUS/TDRS
        into the payload bay of the orbiter  was  accomplished  Aug.  29.
        The Interface Verification Test (IVT) was completed Sept. 4.  The
        End-to-End  Test was run Sept.  6.   The IUS computer memory load
        was performed Sept. 11.  Installation of IUS Flight Batteries was
        completed Sept.  15.   An IUS Redundant Inertial Measurement Unit
        (RIMU) change out was done on Sept. 19.  The final TDRS Joint In-
        tegrated Simulation and IUS countdown simulation   was  performed
        on  Sept.  21.   Final IUS ordnance installation was performed on
        Sept. 24.  The payload bay doors were closed on Sept. 27.


        Deployment History:

             TDRS-C  was  launched  aboard  Discovery  at   11:37   a.m.,
        Thursday,  Sept.  29.   The deployment from Discovery occurred at
        5:50 p.m.  Eastern time on orbit #5.   The ignition the IUS first
        stage  occurred  at  6:50 p.m  with the burn lasting 151 seconds;
        the second stage ignition occurred at 12:08 a.m.  and burned  108
        seconds.    Spacecraft separation came at 12:46 a.m.   On Sunday,
        Oct. 2 there were two burns of the reaction control system.  Burn
        #1 occurred at 8:49 a.m. and lasted 21 minutes.  Burn #2 occurred
        at 8:49 p.m.  and lasted 15 minutes.   These burns began the two-
        week  drift  of the spacecraft toward 150 degrees West for its 85
        day checkout and network integration period.

        STS-26 MID-DECKS:

             The mid-deck experiments were removed from Discovery on Run-
        way 17 before towing to the Dryden Flight Research Facility,  ex-
        cepting the Physical Vapor Trasport of Organic Solids (PVTOS) and
        the Automated Directional Solidifcation Furnace (ADSF) which were
        removed the following day.  The experiments have been returned to
        their principal investigators.



        UPCOMING MISSIONS:


        TDRS-D  (Discovery OV-103)

             TDRS-D  is  at  the TRW plant in Redondo Beach,  California.
        Spacecraft component testing and  shipping  preparations  are  on
        schedule.  Arrival at KSC is now scheduled for November 30.




        MAGELLAN  (Atlantis OV-104)

             The Payload Environmental Transportation System (PETS) which
        has  been  transporting Magellan to the Kennedy Space Center on a
        six-day trip from Denver arrived at KSC this morning about  11:00
        a.m.    It was escorted to the SAEF-2 planetary spacecraft check-
        out facility which is located in the KSC Industrial  Area.    The
        high  gain antenna and ground support equipment which is in other
        trucks in the convoy is being  offloaded today and the PETS  with
        Magellan will be unloaded Sunday morning.