[sci.space.shuttle] Payload Status for 10/18/88

yee@ames.arc.nasa.gov (Peter E. Yee) (10/22/88)

                                 Weekly Payload Status Report
                                 NASA Kennedy Space Center
                                 Tuesday, October 18, 1988


        George Diller


        TDRS-3

             The spacecraft thrusters  were  scheduled  to  be  fired  on
        Saturday,  Oct.  15, to stop the satellite's drift at 150 degrees
        W.  longitude,  which is east of Christmas Island in the Pacific.
        The full checkout of the spacecraft will then begin.   The K-band
        systems have been activated.   Other systems activation  and  as-
        sociated  calibration  in prepartion for the testing is underway.
        The checkout of the spacecraft will be complete on  approximately
        December 25.   At that time the onboard thrusters will once again
        be fired  to begin the drift of the spacecraft to 171 degrees  W.
        longitude where it will be permanently stationed over the equator
        approximately below American Samoa.   There TDRS-3 assumes opera-
        tional status and the  designation  of  TDRS-West.    The  TDRS-3
        spacecraft  at  this  time  is  described  as "healthy."  No sig-
        nificant problems have been identified.



        TDRS-D  (Discovery OV-103)  2/89

             TDRS-D is at the TRW plant  in  Redondo  Beach,  California.
        Spacecraft  component  integration  and  testing will resume next
        week.   Shipping plans are on schedule for an arrival at  KSC  on
        November 30.  The Inertial Upper Stage will arrive on Dec. 10.



        MAGELLAN  (Atlantis OV-104)  4/89

             The Payload Environmental Transportation System (PETS) which
        transported  Magellan  to the Kennedy Space Center on its six-day
        trip from Denver arrived at KSC on Saturday, Oct. 8.   It was es-
        corted to the SAEF-2 planetary spacecraft checkout  facility  lo-
        cated in the KSC Industrial Area.  At that time the high gain an-
        tenna   and  ground  support  equipment  were  offloaded.     The
        spacecraft was removed from the PETS trailer on Sunday.  The com-
        mand and data system has now been installed and checked out.  The
        power control unit was installed Friday and checkout has been un-
        derway.

             At about  11:00  p.m.  on  Monday,  Oct.  17,  the  Magellan
        spacecraft  experienced  a localized electrical fire when workers
        were connecting battery cables.   The  fire  was  quickly  extin-
        guished  and,  at  this  time,  the spacecraft itself appears un-
        damaged.

        The test battery and the associated wire harness  with  connector
        will  have to be replaced.   It is presently believed that during
        the process of connecting  the  battery  cables  to  the  forward
        spacecraft  module  there  was  a short circuit.   This caused an
        overheating of the battery which was  followed  by  smoke  and  a
        small flame.  About five to seven days are estimated to be neces-
        sary  to  recover  from the incident.   There is no impact to the
        launch date.  An investigation board has been appointed.

             The radio transponder used for communication with the ground
        that has been under repair   at  Motorola  was  received  at  KSC
        today. The replacement at Hughes Aircraft of the X-band transmit-
        ter  on  the  spacecraft radar is complete and that unit was also
        received today at  KSC.    These  will  be  integrated  with  the
        spacecraft later, after authorization to proceed is received from
        the board investigating the battery incident.