[sci.space.shuttle] Shuttle Status for 11/01/88

yee@ames.arc.nasa.gov (Peter E. Yee) (11/02/88)

             KSC SPACE SHUTTLE PROCESSING REPORT - TUESDAY, NOV. 1, 1988

                     STS-27  -  ATLANTIS (0V 104)  -  OPF BAY 2

               Preparations are underway today for rolling Atlantis out to
          Launch Pad 39-B at 12:01 a.m. tomorrow.

               Yesterday, technicians removed the piece of wire from the
          left aft structural attach point - one of the three connection
          points between the orbiter and the external tank.  By yesterday
          afternoon, technicians had reconnected the orbiter and tank at
          that attach point, and by 5:30 p.m. the sling was removed from
          the orbiter.

               Today workers are finishing closeouts in the aft compartment
          for the rollout and making minor repairs to the thermal
          protection system on the external tank.

               Atlantis' 4.2 mile long journey from the VAB to Launch Pad
          39-B will take approximately six to seven hours and the shuttle
          vehicle and launch platform are expected to be hard down on the
          pad by 8 a.m. About two hours after hard down the Rotating
          Service Structure will be moved in place around the orbiter.

                       STS-29 - DISCOVERY (OV 103) - OPF BAY 1

               Testing of the orbiter's systems is continuing today
          including checkout of the Ku-band antenna. Preparations are
          underway to begin testing of the power reaction storage and
          distribution system and the auxiliary power unit leak and
          functional checks - both scheduled for later this week.

                        STS-28  -  COLUMBIA (OV 102)  -  OMRF

               Power down modifications are continuing this week including
          crew escape, elevon cove seal, fuel cell improvements, chin panel
          and thermal protection system operations.

                      STS-29 SOLID ROCKET BOOSTERS  -  VAB/RPSF

               Today, the left aft center segment, currently in the VAB
          transfer aisle, is scheduled to be hoisted up to allow inspection
          of the tang. This segment is scheduled to be mated to the left
          aft booster later this week. Final booster buildup operations are
          underway on the right aft booster in the RPSF.