[sci.space.shuttle] Shuttle Status for 11/14/88

yee@ames.arc.nasa.gov (Peter E. Yee) (11/17/88)

             KSC SPACE SHUTTLE PROCESSING REPORT - Monday, Nov. 14, 1988

                      STS-27  -  ATLANTIS (0V 104)  -  PAD 39-B

               The Terminal Countdown Demonstration Test - a dress
          rehearsal of launch day - was performed today. For test purposes,
          the ground launch sequencer stopped the countdown at the T-20
          second mark at about 11:16 a.m. EST.  The countdown clock began
          at 7:40 a.m. yesterday.

               STS-27 flight crew members arrived at KSC on Saturday for
          this standard pre-launch test. While here, they received training
          in emergency escape procedures and were briefed on the status of
          the vehicle elements. Later today, the crew will leave for
          Houston for final pre-launch preparations.

               Today and tomorrow, workers at the pad are scheduled to
          remove and replace a fuel isolation valve for the number two
          auxiliary power unit (APU). This valve - which is one of two that
          feeds hydrazine propellant from the storage tank to the APU -
          stuck open after last week's APU hot fire and needs replacing
          prior to flight. Hydrazine will be drained from APU number two's
          storage tank prior to replacing the valve.

               The Flight Readiness Review is scheduled for tomorrow and
          Wednesday. Shuttle managers from other NASA centers will be
          meeting here at KSC to discuss the readiness of the vehicle
          elements for launch and to establish an official target launch
          date for Mission STS-27.

                       STS-29 - DISCOVERY (OV 103) - OPF BAY 1

               Orbiter systems testing is continuing as scheduled including
          checkout of the water spray boilers, systems testing of the power
          reactant storage and distribution system and functional checks of
          the gaseous oxygen flow control valves.  Technicians are
          preparing to remove the forward reaction control system today so
          the internal plumbing can be cleaned and flushed prior to the
          next flight.

                     STS-28  -  COLUMBIA (OV 102)  -  OPF BAY 2

               Operations are in work to power up the orbiter. Validations
          of the orbiter's electrical system are planned and the payload
          bay doors are scheduled to be opened shortly after power up.
          Orbiter return-to-flight modifications are continuing as planned.

                      STS-29 SOLID ROCKET BOOSTERS  -  VAB/RPSF

               Stacking operations are continuing. The left forward segment
          was stacked last week and the right aft booster was stacked on
          the mobile launcher platform today. The right aft center segment
          was moved into the transfer aisle yesterday and is scheduled to
          be lifted up and hoisted over the stack this week.