[sci.space.shuttle] Gov't contracting problems

eder@ssc-vax.UUCP (Dani Eder) (11/16/88)

In article <3330012@hpindda.HP.COM>, mears@hpindda.HP.COM (David B. Mears) writes:
> > Since this is sci.space.shuttle, the question is then: why isn't Boeing
> > building our shuttles?
> 
> What's really disturbing is not so much that we end up with a product that
> was built by the lowest bidder (with the quality to match) but that the
> contracter always ends up with cost overruns and the thing ends up costing
> more than the higher bidders anyway.  I don't how to do it, but the govt.
> needs to change the way it does contracts so that bidders are forced to
> meet the bids they make along with the quality required.

If you mean Space Shuttle Orbiters, it's because Boeing didn't bid on them.
We bid on the External Tank part of the job, I imagine mostly because at
the time we were building Saturn V first stages in the Michoud, LA facility
where ETs are now built.  If we won the ET contract, then the same people
could have transitioned from Saturn to ET work.   As it happens, we lost
that competition.  Why we did , I don't know, since that happened before
I started working for Boeing.

As to the second quote above, what you should encourage your elected
officials to require is 'firm fixed price' contracting with performance
specifications, but no other types of specifications.

Right now, the contract Boeing has with NASA to build part of the
Space Station is a 'cost plus award fee' type contract.  That means
we bill the government for actual costs incurred in performing the
contract, and our fee (read profit) is determined by a customer
commitee who decide how well we are doing our job.  Imagine
if a car buyer could determine GMs profit based on how happy the
car buyer was.  That would be an equivalent situation.

This type of contract has no inc}ientive to keep costs in line,
in fact, if it costs more to keep the customer happy, and thus
earn a higher award fee, then the incentive is to spend more, since
the gov't will reimburse us for costs.

As far as specifications, generally the gov't overspecifies, which
prevents us from exercising engineering judgement.  We have a
requirments document that is supposed to tell us 'what' the Station
systems are to do.  `But it also includes design solutions, which
prevents us from adopting a better one if we think of it.
ASo the gov't should give us performance specifications, and let
us work out the best way to meet the specs

-- 
Dani Eder / Boeing / Space Station Program / uw-beaver!ssc-vax!eder
(205)464-4150(w) (205)461-7801(h) 1075 Dockside Drive #905 Huntsville, 
AL 35824  34 40 N latitude 86 40 W longitude +100m altitude, Earth

willner@cfa250.harvard.edu (Steve Willner P-316 x57123) (11/18/88)

From article <2369@ssc-vax.UUCP>, by eder@ssc-vax.UUCP (Dani Eder):
> As to the second quote above, what you should encourage your elected
> officials to require is 'firm fixed price' contracting with performance
> specifications, but no other types of specifications.

Absolutely right, but not as simple as it sounds.  See below.
 
> Right now, the contract Boeing has with NASA to build part of the
> Space Station is a 'cost plus award fee' type contract.  That means
> we bill the government for actual costs incurred in performing the
> contract, and our fee (read profit) is determined by a customer
> commitee who decide how well we are doing our job.  
> This type of contract has no incentive to keep costs in line...

In theory, the award fee is supposed to be based on cost as well as
performance, though it's true that in practice it doesn't always work
out that way.

> As far as specifications, generally the gov't overspecifies, which
> prevents us from exercising engineering judgement.  We have a
> requirments document that is supposed to tell us 'what' the Station
> systems are to do.  But it also includes design solutions, which
> prevents us from adopting a better one if we think of it.
> So the gov't should give us performance specifications, and let
> us work out the best way to meet the specs

Having been on the other side of the table, I can say that writing
performance specifications is harder than it sounds.  The problem is
that the specification writers don't generally know the tradeoff
between cost and a particular performance specification.  (Often
nobody knows, if you are trying to do something truly new.)  And of
course, even with perfect knowledge, reasonable people will disagree
whether a certain increment in performance is worth the corresponding
increment in cost.

What we (i.e. the groups in which I have participated) generally do
is try to write 'requirements' and 'goals', the former being the
minimum performance that makes the project worth building and the
latter being the point beyond which no further improvement is
worthwhile.  Unfortunately, it seems impossible in the current
management structure actually to pay on the basis of how closely the
goals are met.  (Contracts for ground-based telescope mirrors HAVE
been written this way with some success; the problem is not primarily
technical, though the technical problems increase greatly when
complex systems are considered rather than single components.) The
alternative of an ongoing, collaborative effort between the users and
the contractor also appears to be unacceptable both to the government
and to the contractors.  (Among other things, the potential for
financial abuse is obvious, and contractors are worried about
disclosing proprietary information.)

Another part of the problem is that NASA seems to be a lot more
capable of auditing financial records than performance records and
writes contracts accordingly.  (Even for basic research grants, for
instance, you need special approval to spend already-allocated money
on something different than in the original budget.)

So what's the bottom line?  Certainly the current process gives too
little incentive to control cost.  Even if incentives were there, the
information available is often inadequate or too late.  No doubt
improvements are possible by using fixed-cost contracts when possible
(and when you can get contractors to bid on them!) and by auditing
performance in preference to cost, but I wouldn't expect any simple
change to give great cost reductions.

-- 
Steve Willner            Phone 617-495-7123         Bitnet:   willner@cfa