[sci.space.shuttle] Shuttle Status for 01/04/89

yee@ames.arc.nasa.gov (Peter E. Yee) (01/07/89)

          KSC SPACE SHUTTLE PROCESSING REPORT FOR - Wednesday, Jan. 4, 1988


                     STS-29  -  DISCOVERY (OV 103)  -  OPF BAY 1

               Power up testing of the orbiter is planned today. Yesterday
          the payload bay doors were opened to allow for final vehicle
          configuration for mission STS-29. A test of the orbiter's power
          redundancy capabilities is one of the operations scheduled today.
          Testing of the main propulsion system and midbody closeouts are
          underway. Other activities scheduled today include, a functional
          test of the waste containment system and thermal protection
          system operations.


                     STS-27  -  ATLANTIS (0V 104)  -  OPF BAY 2

               Today, the orbiter's power system is scheduled to be
          validated, and post flight deconfiguration and inspections are
          planned. Thermal protection system operations are continuing.

                        STS-28  -  COLUMBIA (OV 102)  -  OMRF

               Return-to-flight modifications are continuing today.
          Preparations are underway to deservice the orbiter's freon system
          next week. The system is being deserviced to put the orbiter in
          configuration for installing new thermal protection material
          along the edges of payload bay doors.


                STS-29 and STS-30 SOLID ROCKET BOOSTERS  -  VAB/RPSF

               Final preparations are underway to ready the STS-29 boosters
          and tank for mating with the shuttle Atlantis later this month.

               The left aft booster was stacked on mobile launcher platform
          one yesterday. The left aft center segment is scheduled to be
          stacked this weekend. Meanwhile, technicians are building up the
          right aft booster in the Rotation Processing and Surge Facility.