[sci.space.shuttle] Shuttle Status for 01/11/89

yee@ames.arc.nasa.gov (Peter E. Yee) (01/13/89)

          KSC SPACE SHUTTLE PROCESSING REPORT - WEDNESDAY, JANUARY 11, 1989


                     STS-29  -  DISCOVERY (OV 103)  -  OPF BAY 1

               All but one of the planned tests of the main propulsion
          system in the OPF have been completed and two inspections of the
          main engine oxidizer turbopumps have been completed. The engine
          pump data is being analyzed by NASA and Rocketdyne engineers.

               Preparations for conducting the helium signature leak test
          of the main propulsion system are underway today. That test is
          scheduled to begin tomorrow night. Checks of the tire pressure
          are underway today in preparation for flight. Engineers are
          troubleshooting an oxidizer leak that occurred Monday on one of
          the right orbital maneuvering system thrusters. That leak was
          stabilized and the cause is being investigated.

               Technicians are completing final activities in Discovery's
          payload bay before the doors are closed on Friday for the
          rollover. A functional test of the landing gear is also planned
          on Friday. Rollover to the Vehicle Assembly Building remains
          scheduled for Jan. 19.

                     STS-30  -  ATLANTIS (0V 104)  -  OPF BAY 2

               Post-flight inspections of the vehicle's structure are about
          25 percent complete and inspections of the thermal protection
          system about 80 percent complete. Leak and functional tests of
          the auxiliary power units are underway today.

               Orbiter turnaround processing activities scheduled today
          include a functional test of the star tracker, testing of the
          power reactant storage and distribution system and testing of the
          forward reaction control system.

                        STS-28  -  COLUMBIA (OV 102)  -  OMRF

               Technicians began deservicing the freon cooling system last
          night in preparation for replacing some thermal material on the
          edges of the payload bay doors and the interfacing areas of the
          orbiter. Orbiter return-to-flight modifications are continuing as
          scheduled.

                   STS-29 AND STS-30 SOLID ROCKET BOOSTERS  -  VAB

               Technicians are continuing the closeouts of the STS-29
          boosters and tank. At the request of the Atlantis tile debris
          team headed by John Thomas, some "pull" tests were successfully
          conducted yesterday on the exterior material of the booster nose
          caps and in several areas on the external tank. The team wanted
          to gather data on the bonding of that material to the vehicle
          elements.

               Technicians are continuing the stacking operations for the
          STS-30 solid rocket boosters. Yesterday, the left aft center
          segment was pinned and a leak check of the joint is underway
          today. The left forward center segment arrived in the VAB
          transfer aisle yesterday where preparations to mate are underway.