[sci.space.shuttle] Shuttle Status for 01/13/89

yee@ames.arc.nasa.gov (Peter E. Yee) (01/14/89)

           KSC SPACE SHUTTLE PROCESSING REPORT  - FRIDAY, JANUARY 13, 1989

                     STS-29  -  DISCOVERY (OV 103)  -  OPF BAY 1

               Orbiter processing operations are underway today to support
          transferring Discovery to the Vehicle Assembly Building next
          week. Those operations include the helium signature leak check of
          the main propulsion system, closeouts of the midbody and thermal
          protection system activities.

               This weekend, the helium signature test is scheduled to be
          completed and final closure of the payload bay doors is planned.
          A functional test of the landing gear and a positive pressure
          structural leak check of the orbiter are scheduled next week
          prior to the VAB rollover.


                     STS-27  -  ATLANTIS (0V 104)  -  OPF BAY 2

               Orbiter systems testing is continuing on schedule today as
          part of the turnaround activities to prepare Atlantis for the
          planned April launch.

               Technicians are filling and bleeding the hydraulic system
          and testing the air data probes and the power reactant storage
          and distribution system. Testing of the forward reaction control
          system and the auxiliary power units has been completed.
          Technicians are also repairing damaged tiles.


                        STS-28  -  COLUMBIA (OV 102)  -  OMRF

               Workers are scheduled to begin purging the freon coolant
          loops to configure the system for the replacement of thermal
          material on the edges of the payload bay doors. Orbiter
          modifications are underway. Columbia will be transferred to OPF
          bay 1 a few days after Discovery is towed to the VAB next week.


                   STS-29 and STS-30 SOLID ROCKET BOOSTERS  -  VAB

               Closeouts of the STS-29 boosters and tank are continuing to
          prepare for the orbiter mating operation.

               Booster stacking operations for the STS-30 mission are
          continuing in the VAB high bay and in the transfer aisle.