yee@ames.arc.nasa.gov (Peter E. Yee) (01/25/89)
KSC SPACE SHUTTLE PROCESSING REPORT - FRIDAY, JANUARY 20, 1989 STS-29 - DISCOVERY (OV 103) - OPF BAY 1 Preparations are continuing to move Discovery from the Orbiter Processing Facility to the Vehicle Assembly Building at 12:01 a.m. Sunday. The payload bay doors were closed last night and the landing gear struts have been serviced. Today, tile technicians are scheduled to continue bonding tiles to the orbiter and the payload bay doors. Closeouts of the aft compartment are also continuing in preparation for the move. Once in the VAB transfer aisle, Discovery will be hoisted up with an overhead crane and positioned in between the tank and boosters. STS-30 - ATLANTIS (0V 104) - OPF BAY 2 Systems testing of the orbiter Atlantis has continued this week. Operations scheduled today include leak and functional tests of the auxiliary power units, payload bay operations, preparations to check out the left hand orbital maneuvering system pod and removal of the remote manipulating system. STS-28 - COLUMBIA (OV 102) - OMRF Technicians are preparing the orbiter Columbia for the move to OPF bay 1 on Sunday evening. While in the OPF, Columbia will be powered up for check out of the newly modified systems. STS-29 AND STS-30 SOLID ROCKET BOOSTERS - VAB Final closeouts are underway on the STS-29 tank and boosters in preparation for mating with the orbiter Discovery on Sunday. Preparations are underway to stack the left forward segment to the STS-30 stack this weekend.