[sci.space.shuttle] Shuttle Status for 02/09/89

yee@ames.arc.nasa.gov (Peter E. Yee) (02/10/89)

          KSC SPACE SHUTTLE PROCESSING REPORT - THURSDAY, FEBRUARY 9, 1989

                        STS-29  -  DISCOVERY (OV 103)  -  VAB

               All three oxidizer turbo pumps have been removed from the
          orbiter. Testing of the new pumps is in progress this week at the
          Stennis Space Center in Mississippi. Delivery of the new pumps is
          expected next week.

               Workers at the pad are making preparations for the pre-
          launch propellant load activity scheduled this weekend. This
          operation includes loading hydrazine into Discovery's auxiliary
          power units and the solid rocket boosters' hydraulic power units.
          Monomethylhydrazine and nitrogen tetroxide will be loaded into
          Discovery's reaction control system and orbital maneuvering
          system storage tanks.  The payload bay doors are scheduled to be
          closed today for the hyper load operation.

               The Tracking and Data Relay Satellite and its Inertial Upper
          Stage were installed in the payload bay Monday. Communications
          checks were completed yesterday between the pad and the IUS
          checkout station on the Cape Canaveral Air Force Station. Those
          checks are in preparation for payload testing next week.


                     STS-30  -  ATLANTIS (0V 104)  -  OPF BAY 2

               Workers have installed two main engines and are scheduled to
          install the third engine today. Preparations are underway to
          service the orbiter's ammonia boilers this weekend. Thermal
          protection system operations are continuing and the cavity count
          was at 60 this morning.


                     STS-28  -  COLUMBIA (OV 102)  -  OPF BAY 1

               Power up testing of Columbia is continuing today. Checks of
          the main propulsion system and the communications and navigations
          systems are planned.


                        STS-30 SOLID ROCKET BOOSTERS  -  VAB

               Technicians are leveling the right aft center segment in
          preparation for mating to the right aft booster. Meanwhile,
          technicians in the RPSF are preparing the right forward segment
          for stacking.