[sci.space.shuttle] Shuttle Status for 02/10/89

yee@ames.arc.nasa.gov (Peter E. Yee) (02/11/89)

           KSC SPACE SHUTTLE PROCESSING REPORT - FRIDAY, FEBRUARY 10, 1989

                        STS-29  -  DISCOVERY (OV 103)  -  VAB

               Workers at the pad are making preparations for the pre-
          launch propellant load activity scheduled this weekend. This
          operation includes loading hydrazine into Discovery's auxiliary
          power units and the solid rocket boosters' hydraulic power units.
          Monomethylhydrazine and nitrogen tetroxide will be loaded into
          Discovery's reaction control system and orbital maneuvering
          system storage tanks.  The payload bay doors were closed last
          night for the hyper load operation.

               Testing of the new pumps is in progress this week at the
          Stennis Space Center in Mississippi. The first new pump is
          expected on Monday. New pumps will go through receiving
          inspections prior to installation on the engines. Installation of
          the three pumps and the associated testing is scheduled to be
          completed prior to the end of this month.

               Tests of the Tracking and Data Relay Satellite and its
          Inertial Upper Stage are scheduled next week in parallel with
          pump installation activities.


                     STS-30  -  ATLANTIS (0V 104)  -  OPF BAY 2

               Workers have installed all three main engines and are
          scheduled to electrically connect the engines to the orbiter
          today. Preparations are underway to service the orbiter's ammonia
          boilers this weekend. Thermal protection system operations are
          continuing.


                     STS-28  -  COLUMBIA (OV 102)  -  OPF BAY 1

               Power up testing of Columbia is continuing today. Checks of
          the main propulsion system and the communications and navigations
          systems are planned. Technicians are servicing the freon cooling
          loops.


                        STS-30 SOLID ROCKET BOOSTERS  -  VAB

               Yesterday, the right aft center segment was mated to the
          right aft booster. The right forward center segment and the right
          forward assembly were moved into the VAB transfer aisle and are
          being inspected.