[sci.space.shuttle] Shuttle Status for 03/28/89

yee@trident.arc.nasa.gov (Peter E. Yee) (03/29/89)

            KSC SPACE SHUTTLE PROCESSING REPORT - TUESDAY, MARCH 28, 1989

                      STS-30  -  ATLANTIS (0V 104)  -  PAD 39-B

               Technicians at the pad have installed two of three high
          pressure oxidizer turbo pumps (HPOTP) on the main engines. The
          third HPOTP will be installed after hypergolic propellants have
          been loaded onboard the ship.

               Preparations are underway for loading nitrogen tetroxide and
          monomethylhydrazine into Atlantis' onboard storage tanks. As part
          of the hazardous propellant loading operation, hydrazine will be
          loaded into the orbiter's auxiliary power units and the booster
          hydraulic power units. The actual loading operation is scheduled
          to begin Wednesday evening and all day Thursday.

               The Countdown Demonstration Test is scheduled to begin with
          a call-to-stations at 8 a.m. April 6 and will culminate at 11
          a.m. April 7 with a simulated engine cutoff.

                     STS-28  -  COLUMBIA (OV 102)  -  OPF BAY 1

               Power up testing planned this week includes check out of the
          power reactant storage and distribution system, water spray
          boilers, a functional test of the waste containment system and
          leak and functional tests of the auxiliary power units.  Retest
          of the master events controller has been completed. Technicians
          are preparing the orbiter's cavity for installation of the
          forward reaction control system Wednesday night.

                       STS-33 - DISCOVERY (OV 103) - OPF BAY 2

               Power up operations are scheduled today. Preparations for
          activating the orbiter's hydraulic system are underway. The body
          flap will be positioned to allow removal of the tail cone. The
          payload bay door strongbacks were installed yesterday and the
          payload bay doors are scheduled to be opened later this week.
               The three main engines will be removed next week and engine
          one will be sent back to the Rocketdyne plant in Canoga Park,
          Calif. for analysis and repair of a crack in its main combustion
          chamber. A new engine will be sent for Discovery's next flight.

                        STS-28 SOLID ROCKET BOOSTERS  -  RPSF

               Buildup operations are continuing on the left and right aft
          boosters. Technicians are scheduled to begin stacking segments
          next week with the left aft booster in VAB high bay 1.

               At Hangar AF, the STS-29 segments have been disassembled in
          preparation for shipment back to Morton Thiokol in Utah for
          refurbishment. The segments will go back by rail this week.