[sci.space.shuttle] Shuttle Status for 04/10/89

yee@trident.arc.nasa.gov (Peter E. Yee) (04/11/89)

            KSC SPACE SHUTTLE PROCESSING REPORT - MONDAY, APRIL 10, 1989

                      STS-30  -  ATLANTIS (0V 104)  -  PAD 39-B

               This past weekend, Magellan and Inertial Upper Stage end-to-
          end test was successfully completed.  The Terminal Countdown
          Demonstration Test was conducted Friday with a simulated engine
          cutoff at 11 a.m.

               Main engine technicians are conducting leak checks of the
          three engines to check out the new high pressure oxidizer turbo
          pumps. Engine readiness tests are planned for mid-week and heat
          shields will be installed around the engines later this week. A
          helium signature leak check of the main propulsion system is
          planned for early next week.


                     STS-28  -  COLUMBIA (OV 102)  -  OPF BAY 1

               Orbiter systems testing is continuing this week including
          checkout of the Ku-band antenna, water spray boilers, air
          revitalization system and power reactant storage and distribution
          system. Installation of the orbiter's radiators are scheduled
          this week. Thermal protection system operations are continuing.
          Work is underway to prepare the two orbital maneuvering system
          pods for installation on the orbiter.


                        STS-33 DISCOVERY (OV 103) - OPF BAY 2

               Technicians successfully offloaded hypergolic propellants
          this weekend. Structural post-flight inspections and window
          polishing are scheduled this week.


                      STS-28 SOLID ROCKET BOOSTERS  -  VAB/RPSF

               The left aft center segment was stacked on the left aft
          booster over the weekend. The left forward center segment is
          scheduled to be transferred to the VAB today and stacked on the
          left booster this week. Meanwhile, other segments are being
          prepared for stacking in the RPSF.