[sci.space.shuttle] Shuttle Status for 07/07/89

yee@trident.arc.nasa.gov (Peter E. Yee) (07/08/89)

             KSC SPACE SHUTTLE PROCESSING REPORT - FRIDAY, JULY 7, 1989

                        STS-28  -  COLUMBIA (OV 102)  -  VAB

               Technicians successfully connected the liquid oxygen
          electrical interfaces between the shuttle and the external tank.
          Final connection operations are in work today to prepare for
          powering up the orbiter tomorrow. Tile step and gap measurements
          are being taken, gap fillers are being installed in various areas
          and tile repairs are underway.

               The Shuttle Interface Test is scheduled to begin no earlier
          than tomorrow morning. The purpose of the test is to verify all
          critical connections between the orbiter and the tank, orbiter
          and boosters, orbiter and mobile launcher platform and to perform
          a functional operation check of the solid rocket boosters'
          systems.

               Columbia's rollout is currently targeted for no earlier than
          12:01 a.m. Wednesday, July 12.

                      STS-34  -  ATLANTIS (OV 104) - OPF BAY 2

               Two of the three main engines have been installed and
          the third is scheduled for installation today. Preparations are
          underway to remove the left orbital maneuvering system pod this
          weekend. Operations continuing today include a leak test of the
          environmental control system, a functional check of the waste
          containment system and check out of the forward reaction control
          system.

                       STS-33  -  DISCOVERY (OV 103)  -  OMRF

               Power down work is continuing this week in the OMRF to
          prepare Discovery for transfer to OPF bay 1 on Monday.
          Preventative maintenance is being performed on equipment used in
          bay 1, including the telescoping buckets used for access to the
          payload bay.

                       STS-34 SOLID ROCKET BOOSTERS - VAB/RPSF

               Stacking operations are continuing on a non-interference
          basis with STS-28 shuttle mating activities. The left forward
          assembly has been mated to the stack and joint closeouts are active.