[sci.space.shuttle] Shuttle Status for 07/28/89

yee@trident.arc.nasa.gov (Peter E. Yee) (07/29/89)

             KSC SPACE SHUTTLE PROCESSING REPORT - FRIDAY, JULY 28, 1989

                  STS-28  -  COLUMBIA (OV 102)  -  LAUNCH PAD 39-B

               Technicians at Launch Pad 39-B are continuing the welding
          operation to replace two valves in the aft compartment for the
          main propulsion system helium system. A new line was brazed in
          earlier this week and a filter was replaced. A new helium
          regulator will be installed after the welding activities are
          completed. These components are being replaced because of
          contamination found in the system several weeks ago. An engine
          frequency response test is planned for Monday to cycle valves and
          check out acutators.

               Tomorrow, technicians are scheduled to install some of the
          ordnance devices, load the power reactant storage and
          distribution system tanks on the Fixed Service Structure with
          liquid oxygen and liquid hydrogen, and pressurize the orbiter's
          onboard hypergolic propellant storage tanks for flight.

               Launch countdown preparations will begin next week. Launch
          of Columbia and mission STS-28 is scheduled for August 8 with a
          launch period of 7:30 a.m. to 11:30 a.m. eastern time.

                      STS-34  -  ATLANTIS (OV 104) - OPF BAY 2

               The left orbital maneuvering system pod is being installed
          and checkout is planned next week. Checkout of the water spray
          boilers and waste containment system are continuing this week. A
          helium signature test of the main engines is planned next week.

                     STS-33  -  DISCOVERY (OV 103)  -  OPF BAY 1

               Power up operations and systems testing are planned today. A
          voltage test of the fuel cells was completed. A functional check
          of the forward reaction control system is continuing.
          Modifications and tile work are underway. Testing of the Ku-band
          antenna is planned next week.

                       STS-34 SOLID ROCKET BOOSTERS - VAB/RPSF

               Joint closeouts are active on all booster field joints.
          Mating of the external tank to the boosters is scheduled for this
          weekend.