[sci.space.shuttle] Shuttle Status for 08/02/89

yee@trident.arc.nasa.gov (Peter E. Yee) (08/04/89)

            KSC SPACE SHUTTLE PROCESSING REPORT - WEDNESDAY, AUG. 2, 1989

                  STS-28  -  COLUMBIA (OV 102)  -  LAUNCH PAD 39-B

               Yesterday, the engine frequency response test (FRT) began at
          about 1 p.m. and was completed by late yesterday. During this
          test, engine valves were cycled and actuators were checked out.
          The orbiter's aerosurfaces were cycled this morning and
          preparations are underway to perform leak checks of seals around
          the engine valves.

               Later today, checks of the range safety system will be
          conducted. Retest of the liquid hydrogen external tank actuator,
          which separates the tank from the orbiter in flight, is scheduled
          for tonight. Retest of that particular actuator requires the use
          of the master events controller (MEC) which is responsible for
          sending the separation command in flight. The pad will be closed
          tonight while technicians disconnect ordnance devices to allow
          retest of the actuator through the MEC. After the retest,
          ordnance devices will be reconnected and final ordnance
          operations are scheduled for tomorrow.

                Sniff checks of the orbital maneuvering system fuel motor
          valves were completed yesterday. (Yesterday's status incorrectly
          refered to orbital maneuvering system pod motor valves as liquid
          oxygen and hydrogen. They are hypergolic and fuel valves.)

               Launch countdown preparations are underway this week. The
          mobile launcher platform was washed down yesterday. Today, the
          flame trench and pad surface are scheduled to be washed down. The
          countdown is scheduled to begin at 12:01 a.m. eastern time
          Saturday morning and the STS-28 flight crew members will be
          arriving at KSC's Shuttle Landing Facility at about 4 p.m. that
          afternoon. Launch of Columbia on mission STS-28 is scheduled for
          August 8 with a launch period of 7:30 a.m. to 11:30 a.m. eastern
          time.

                      STS-34  -  ATLANTIS (OV 104) - OPF BAY 2

               Preparations for the helium signature leak test of the main
          engines are underway today. An electrical redundancy test of the
          OMS and FRCS is scheduled this week. Thermal blankets are being
          installed on the aft bulkhead and on the cooling lines for the
          radioisotope thermoelectric generators.

                     STS-33  -  DISCOVERY (OV 103)  -  OPF BAY 1

               Power up operations and systems testing are planned today.
          Filling and bleeding of the hydraulic system are underway.
          Modifications and tile work are underway. Testing of the Ku-band
          antenna is underway this week.

                  STS-34 SOLID ROCKET BOOSTERS/EXTERNAL TANK - VAB

               Technicians are making electrical connections between the
          boosters and tank.


                         STS-33 SOLID ROCKET BOOSTERS - RPSF

               Buildup of the left and right aft boosters for the STS-33
          mission is continuing at the Rotation Processing and Surge
          Facility. Stacking is scheduled to begin later this month.