yee@trident.arc.nasa.gov (Peter E. Yee) (08/18/89)
KSC SPACE SHUTTLE PROCESSING REPORT - THURSDAY, AUG. 17, 1989
STS-28 - COLUMBIA (OV 102) - DFRF
Turnaround activities are continuing on schedule at Dryden
Flight Research Facility for returning the Columbia to KSC this
weekend. Hypergolic propellants were offloaded yesterday and
preparations are underway to install the aerodynamic tail cone
over the three main engines. Columbia will be bolted on top of
the 747 Shuttle Carrier Aircraft tomorrow.
Pending the completion of planned work and favorable
weather, the cross-country ferry flight will begin on Saturday
morning. A refueling stop is planned at Sheppard Air Force Base,
Wichita Falls, Texas. A one-day ferry flight is desirable pending
favorable weather.
STS-34 - ATLANTIS (OV 104) - OPF BAY 2
A functional test of the landing gear is planned for
tonight. Hydraulic operations will continue tomorrow with
positioning the orbiter's aerosurfaces for the roll over.
The gaseous oxgyen lines in engine 2027 are being inspected
for a few micron size particles that could have come from some
ground support equipment during testing.
A tile was bonded on the right hand nose landing gear door
yesterday. Step and gap measurements are being made and gap
fillers are being installed. This morning, 9 tile cavities were
reported.
Schedulers are targeting to move Atlantis to the Vehicle
Assembly Building early in the morning on Sunday, August 20. A
specific time will be determined as work progresses. Atlantis is
scheduled to be in the VAB about eight days before being
transferred to Launch Pad 39-B. While in the VAB, Atlantis will
be bolted to its solid rocket boosters and external tank.
STS-33 - DISCOVERY (OV 103) - OPF BAY 1
Power up operations and systems testing are planned today.
Modifications and tile work are underway. Operations scheduled
this week include testing of the waste containment system and the
Ku-band antenna system. Three of the four main landing gear tires
were installed.
Two of the three main engines are scheduled to be installed
tomorrow and Saturday. The right orbital maneuvering system pod
is scheduled to be installed next week.
STS-34 SOLID ROCKET BOOSTERS/EXTERNAL TANK - VAB
Closeouts of the STS-34 external tank and solid rocket
boosters are underway this week. Cable tray covers are being
closed out for flight. Orbiter mate preparations have begun.
STS-33 SOLID ROCKET BOOSTERS - VAB
The left aft center segment was transferred to the VAB early
this morning and is being prepared for mating. Booster stacking
operations will continue on a non-interference basis with the
STS-34 orbiter mating activities.yee@trident.arc.nasa.gov (Peter E. Yee) (08/18/89)
Oops. Looks like I got the date wrong on the subject line. Ignore the subject line and read the status report. -Peter Yee yee@ames.arc.nasa.gov ames!yee
yee@trident.arc.nasa.gov (Peter E. Yee) (08/19/89)
KSC SPACE SHUTTLE PROCESSING REPORT - FRIDAY, AUG. 18, 1989
STS-28 - COLUMBIA (OV 102) - DFRF
Turnaround activities are continuing on schedule at Dryden
Flight Research Facility for returning the Columbia to KSC this
weekend. The aerodynamic tail cone has been installed over the
three main engines and preparations are underway to position the
body flap for the ferry flight. Columbia will be bolted on top of
the 747 Shuttle Carrier Aircraft tonight.
Pending the completion of planned work and favorable
weather, the cross-country ferry flight will begin early
Saturday morning. A refueling stop is planned at Sheppard Air
Force Base, Wichita Falls, Texas. A one-day ferry flight is
planned, pending favorable weather, putting Columbia's arrival
back at KSC tomorrow evening before sunset.
STS-34 - ATLANTIS (OV 104) - OPF BAY 2
Rollover preparations are underway today. A functional test
of the landing gear is underway after which the landing gear
doors will be cycled for tile fit checks. The orbiter's
aerosurfaces have been positioned for the rollover.
The gaseous oxgyen lines in engine 2027 are being inspected
for a few micron size particles that could have come from some
ground support equipment during testing.
Six tiles are scheduled to be bonded today. Step and gap
measurements are being made and gap fillers are being installed.
This morning, 9 tile cavities were reported.
Schedulers are targeting to move Atlantis to the Vehicle
Assembly Building at midnight Saturday. Atlantis is scheduled to
be in the VAB about eight days before being transferred to Launch
Pad 39-B. While in the VAB, Atlantis will be bolted to its solid
rocket boosters and external tank.
STS-33 - DISCOVERY (OV 103) - OPF BAY 1
Power up operations and systems testing are planned today.
Modifications and tile work are underway. The waste containment
system has been installed.
Preparations are underway to install engine 2107 in the
number three position today. The second engine will be installed
in the number one position tomorrow. The third main engine is
scheduled to arrive the last week of the month. The right orbital
maneuvering system pod is scheduled to be installed next week.
STS-34 SOLID ROCKET BOOSTERS/EXTERNAL TANK - VAB
Preparations to mate the orbiter to the external tank are
scheduled today. Platforms around the tank and boosters will be
retracted tomorrow afternoon in preparation for the mate.
Atlantis will be hardmated to the stack about 27 hours after it
arrives in the transfer aisle.
STS-33 SOLID ROCKET BOOSTERS - VAB
The left aft center segment is scheduled to be lifted for
inspections today and mated by tomorrow evening. Booster stacking
operations will continue on a non-interference basis with the
STS-34 orbiter mating activities.