[sci.space.shuttle] Shuttle Status for 08/23/89

yee@trident.arc.nasa.gov (Peter E. Yee) (08/24/89)

           KSC SPACE SHUTTLE PROCESSING REPORT  - WEDNESDAY AUG. 23, 1989

                     STS-32  -  COLUMBIA (OV 102)  -  OPF BAY 2

               Access platforms are being positioned around the vehicle.
          Preparations for post-flight frequency response test of the
          aerosurfaces and preparations to remove the protective tail cone
          are underway today.  Inspections of the main engine's main
          combustion chamber are scheduled today.  The three main engines
          are scheduled to be removed next week and taken to the VAB main
          engine shop for post flight inspection and for replacement of
          several components.


                        STS-34  -  ATLANTIS (0V 104)  -  VAB

               The liquid hydrogen mobile launcher pad tail service mast
          has been mated to Atlantis and electrical connections of the
          liquid oxygen tail service mast are in work.  Ordnance devices
          are being installed between the orbiter and external tank.
          Required purges have been initiated to the crew cabin, payload
          bay and aft compartment.  Orbiter to external tank electrical
          connections are scheduled for later today.  Power up testing to
          verify connections is planned for tomorrow.

               At the Verticle Processing Facility, technicians are
          scheduled to load the Galileo/IUS payload into the payload
          canister today.  The canister laden with the Jupiter-bound
          spacecraft is scheduled to be transferred to Launch Pad 39-B at
          12:01 a.m. Friday, August 25, 1989.

               Atlantis is scheduled to be transferred to Launch Pad 39-B
          at 12:01 a.m., Monday, August 28, 1989.

                     STS-33  -  DISCOVERY (OV 103)  -  OPF BAY 1

               Several components were installed yesterday including the
          right Orbital Maneuvering Systems Pod, the galley, and two of
          three auxiliary power unit controllers.  A functional test of the
          galley and interface verification of the Orbital Maneuvering
          Systems Pod are scheduled today.  Other activities planned today
          include leak and functional testing of the waste containment
          system, inspection of payload bay thermal blankets and tile
          operations.

                        STS-33 SOLID ROCKET BOOSTERS  -  VAB

               The left forward center segment is scheduled to be stacked
          today.  Booster stacking operations will continue on a
          non-interference basis with the STS-34 orbiter mating activities.