[sci.space.shuttle] Shuttle Status for 08/24/89

yee@trident.arc.nasa.gov (Peter E. Yee) (08/25/89)

            KSC SPACE SHUTTLE PROCESSING REPORT - THURSDAY, AUG. 24, 1989

                       STS-32 - COLUMBIA (OV 102) - OPF BAY 2

               Columbia is scheduled to be powered up today for post-flight
          testing. The strongbacks are being attached to the payload bay
          doors for opening next week. Preparations are underway to remove
          the protective tailcone tonight after the body flap has been
          positioned. Heatshields are scheduled to be removed from around
          the main engines this weekend and the engines will be removed
          next week.

                         STS-34  -  ATLANTIS (OV 104) - VAB

               The liquid hydrogen and oxygen tail service masts have been
          mated to the orbiter and electrical connections between the
          orbiter and external tank are underway. Power up testing is
          planned tomorrow.

               At the Vertical Processing Facility, the Galileo/Inertial
          Upper Stage payload was installed in the payload canister today.
          At about midnight, the canister will be transferred to Launch Pad
          39-B.

                Atlantis is scheduled to be transferred to Launch Pad 39-B
          at 12:01 a.m. Monday, August 28.

                     STS-33  -  DISCOVERY (OV 103)  -  OPF BAY 1

               Interface verification checks of the right orbital
          maneuvering system pod are underway. Other activities scheduled
          today include leak and functional testing of the auxiliary power
          units, orbiter modifications and thermal protection system
          operations. Technicians are installing heat shields around
          engines one and three. The nose landing gear wheels and tire
          assemblies are scheduled to be installed this week.

                         STS-33 SOLID ROCKET BOOSTERS - VAB

               The left forward center segment is scheduled to be lifted
          today for pre-mating inspections. The right aft booster is being
          prepared at the RPSF for transfer to the VAB this weekend.
          Booster stacking operations will continue on a non-interference
          basis with the STS-34 orbiter mating activities.