[sci.space.shuttle] Shuttle Status for 08/25/89

yee@trident.arc.nasa.gov (Peter E. Yee) (08/26/89)

             KSC SPACE SHUTTLE PROCESSING REPORT - FRIDAY, AUG. 25, 1989

                         STS-34  -  ATLANTIS (OV 104) - VAB

               Electrical connections between the tank and orbiter have
          been completed and closeouts are underway.  Power up testing is
          planned for this evening to verify the critical connections
          between the orbiter and tank and orbiter and mobile launcher
          platform. Yesterday, engineers worked to resolve the
          configuration of a connecting pin on the liquid oxygen electrical
          connector between the tank and orbiter.

               At the Vertical Processing Facility, the Galileo/Inertial
          Upper Stage payload was transferred to Launch Pad 39-B early
          this morning and is being installed in the Payload Changeout
          Room today. Installation into the orbiter's payload bay is
          scheduled for Aug. 30.

                Because of the time required to resolve the liquid oxygen
          electrical connector issue, Atlantis' move to Launch Pad 39-B has
          been moved 24 hours, with first motion at 12:01 a.m. Tuesday,
          August 29.

                     STS-33  -  DISCOVERY (OV 103)  -  OPF BAY 1

               Interface verification checks of the right orbital
          maneuvering system pod are underway. Other activities scheduled
          today include leak and functional testing of the auxiliary power
          units, orbiter modifications and thermal protection system
          operations. Technicians are installing heat shields around
          engines one and three. Engine number 2 is scheduled to arrive
          early next week and will be installed shortly afterwards. The
          nose landing gear wheels and tire assemblies are scheduled to be
          installed this weekend.

                       STS-32 - COLUMBIA (OV 102) - OPF BAY 2

               Columbia was powered up yesterday for post-flight testing.
          The protective tailcone was removed yesterday. Heatshields are
          scheduled to be removed from around the main engines this weekend
          and the engines will be removed next week. They will be taken to
          the VAB main engine shop for post-flight inspections and for the
          replacement of several components. Also next week, the flight
          tires will be removed.

                         STS-33 SOLID ROCKET BOOSTERS - VAB

               The left forward center segment was lifted into the high bay
          over the stack where mating activities are underway. The segment
          will be pinned to the stack tomorrow. The right aft booster is
          being prepared at the RPSF for transfer to the VAB this weekend.
          Booster stacking operations will continue on a non-interference
          basis with the STS-34 orbiter mating activities.