[sci.space.shuttle] Shuttle Status for 09/19/89

yee@trident.arc.nasa.gov (Peter E. Yee) (09/20/89)

            KSC SPACE SHUTTLE PROCESSING REPORT - TUESDAY, SEPT. 19, 1989

                       STS-34  -  ATLANTIS (OV 104) - PAD 39-B

               Preparations are underway to button up the orbiter for
          adverse weather or for a roll back to the Vehicle Assembly
          Building. The payload bay doors are scheduled to be closed this
          morning, platforms are being retracted and loose items are being
          secured. Servicing and testing of the cooling system for
          Galileo's radioisotope thermoelectric generators was completed
          yesterday. Deservicing of that cooling system is scheduled today.

               Earlier today, one of the two crawler transporters was moved
          to the Pad B gate in the event a decision to roll back to the VAB
          is made. That decision is expected tomorrow.

                     STS-33  -  DISCOVERY (OV 103)  -  OPF BAY 1

               Electrical redundancy testing of the orbital maneuvering
          system and reaction control systems is scheduled this week.
          Orbiter systems testing and thermal protection system operations
          are continuing.

                       STS-32 - COLUMBIA (OV 102) - OPF BAY 2

               Operations scheduled this week include functional checks of
          the water spray boilers, leak and functional tests of the main
          propulsion system and thermal protection system operations.
          Preparations are underway to install the remote manipulator
          system in a few weeks.

                         STS-33 SOLID ROCKET BOOSTERS - VAB

               The right forward assembly/nose cone was pinned to the right
          forward segment early this morning. Technicians are closing out
          the joints on the right and left boosters for flight. The
          external tank is scheduled to be mated on Sept. 23.

                         STS-32 SOLID ROCKET BOOSTERS - VAB

               Early this morning the left aft booster was removed from
          mobile launcher platform 3 in the Vehicle Assembly Building. This
          action was taken due to the possiblity of Atlantis rolling back
          to the VAB. MLP-3 may be moved to a parksite outside the VAB to
          make room for Atlantis. A crawler transporter was moved outside
          the VAB for the possible MLP-3 move. Transfer of the left aft
          center segment to the VAB has been postponed.