[sci.space.shuttle] Shuttle Status for 11/01/89

yee@trident.arc.nasa.gov (Peter E. Yee) (11/02/89)

            KSC SPACE SHUTTLE PROCESSING REPORT - WEDNESDAY, NOV. 1, 1989

                     STS-33  -  DISCOVERY (OV 103)  -  PAD 39-B

               Operations to load hypergolic propellants aboard Discovery
          for flight are underway today. Later today, the pad will be
          cleared of all non-essential personnel while nitrogen tetroxide
          and monomethylhydrazine are loaded in the orbital maneuvering
          system and reaction control system storage tanks. Also during
          this operation, hydrazine will be loaded onboard for Discovery's
          auxiliary power units and for the solid rocket boosters'
          hydraulic power units. One of the two hydraulic power units on
          the left hand solid rocket booster was replaced last week after
          it was discovered that the unit came from a lot that produced at
          least one unit with a cracked housing. This unit will be hot
          fired after the propellant loading operation.  Ths activity is
          scheduled through Friday.

               Yesterday, technicians installed heat shields around the
          number 2 main engine and finished securing the high pressure
          oxidizer turbo pump on engine 3. A helium signature leak test of
          the main propulsion system and main engines is scheduled for
          Monday.

               Shuttle managers will meet at KSC on Nov. 6-7 for the Flight
          Readiness Review to assess the readiness for the safe and
          successful conduct of the STS-33 launch, mission, landing and
          recovery.  An official launch date is also expected to be
          announced at the conclusion of the review.

                     STS-36  -  ATLANTIS (0V 104)  -  OPF BAY 1

               Power up of the orbiter is planned for today along with
          preparations to remove the protective tail cone. Operations are
          underway to activate the hydraulic system to lower the body flap
          for tail cone removal. Technicians are also preparing to open the
          payload bay doors.

                     STS-32  -  COLUMBIA (OV 102)  -  OPF BAY 2

               Testing of the orbiter's hydraulically operated systems is
          underway this week. Yesterday, tests of the orbiter's
          aerosurfaces/flight controls system and a test of the main
          propulsion system thrust vector control system were conducted.
          Preparations are underway to conduct a flight readiness test of
          the three main engines.  Closeouts of the midbody and
          final thermal protection system operations are underway. Rollover
          to the Vehicle Assembly Building is planned in about two weeks.


                 STS-32 SOLID ROCKET BOOSTERS/EXTERNAL TANK  -  VAB

               Mating operations began this morning for the external tank
          and solid rocket boosters. "Soft-mate" is scheduled for tomorrow
          morning. Checks of the mechanical and electrical connections will
          be conducted after the mate. The orbiter is scheduled to be mated
          in the next few weeks.


                         STS-36 SOLID ROCKET BOOSTERS - RPSF

               Technicians are building up the left and right aft solid
          rocket boosters. Stacking is scheduled to begin with the left aft
          booster this weekend.