yee@trident.arc.nasa.gov (Peter E. Yee) (11/15/89)
KSC SPACE SHUTTLE PROCESSING REPORT - TUESDAY, NOV. 14, 1989 STS-33 - DISCOVERY (OV 103) - PAD 39-B Engineers are preparing to remove the two aft integrated electronics assemblies (IEAs) from the left and right solid rocket boosters. The IEAs act as the brain for the booster by routing power, commands and data between the orbiter and boosters. It was discovered by the vendor that wiring in these two aft units could potentially have been routed such that some wires could rub against hardware which could cause a short. Once removed, these units will be transferred to the USBI facility where inspectors from Bendix will verify the wiring. Today, workers are removing closeout material, or foam, from the IEAs to gain access to these units located in the vicinity of the external tank attach ring. Later, ordnance devices on the vehicle will be disconnected and the IEAs can be removed. Closeouts of the aft compartment for flight are underway. Purges of the power reactant storage and distribution system tanks have been completed. The launch date of mission STS-33 is being evaluated at this time but is now no earlier than November 22, 1989. STS-36 - ATLANTIS (0V 104) - OPF BAY 1 The last main engine was removed yesterday and taken to the engine shop in the VAB where all three engines will undergo post- flight checks. Deservicing of residual hypergolic propellants is planned this week. Checks of the main propulsion system and communications system are scheduled this week. STS-32 - COLUMBIA (OV 102) - OPF BAY 2 Closeouts of the vehicle for the move to the Vehicle Assembly Building are underway. Workers are preparing thermal barriers around the landing gear doors and weight and center of gravity operations are planned for early tomorrow. The orbiter transporter will be used to transfer the orbiter from the OPF to the Vehicle Assembly Building on November 16. STS-32 SOLID ROCKET BOOSTERS/EXTERNAL TANK - VAB Two of the IEAs on this set of boosters could also have the same wiring problem. These two units are being removed today for inspections and will not be reinstalled until the STS-33 units have been cleared for flight. STS-36 SOLID ROCKET BOOSTERS - VAB The left forward center was transferred to the VAB and stacking preparations are underway. The right aft booster is being built up in the Rotation Processing and Surge Facility.
tneff@bfmny0.UU.NET (Tom Neff) (11/15/89)
In article <35856@ames.arc.nasa.gov> yee@trident.arc.nasa.gov (Peter E. Yee) writes: > It was discovered by the vendor that wiring in these two > aft (IEA) units could potentially have been routed such that some > wires could rub against hardware which could cause a short. Once > removed, these units will be transferred to the USBI facility ... > The launch date of mission STS-33 is being evaluated at this > time but is now no earlier than November 22, 1989. Oh boy... What's the window for LDEF these days? Would there be a scheduling impact on subsequent missions if this SIGINT launch has to wait, say, two weeks? If anyone knows, pipe up... -- Stalinism begins at home. }{ Tom Neff }{ tneff@bfmny0.UU.NET