[sci.space.shuttle] Shuttle Status for 12/12/89

yee@trident.arc.nasa.gov (Peter E. Yee) (12/14/89)

                 KSC SHUTTLE STATUS REPORT - TUESDAY, DEC. 12, 1989

                        STS-32 - COLUMBIA (OV 102) - PAD 39-A

               Hypergolic propellant loading activities are continuing
          today. Yesterday, nitrogen tetroxide propellants were loaded into
          storage tanks for the reaction control system and orbital
          maneuvering system. Today, monomethylhydrazine, the fuel, is
          being loaded aboard the orbiter.  In addition, hydrazine will be
          loaded in tanks for the orbiter's auxiliary power units and for
          the boosters' hydraulic power units. This hazardous operation,
          scheduled through tonight, requires that the pad be closed of all
          non-essential personnel.

               Early tomorrow morning, the solid rocket boosters' hydraulic
          power units will be "hot fired," or run, for about 20-30 seconds.
          The hot fire is necessary because the HPUs were replaced due to a
          concern with a cracked housing. Also, one of the integrated
          electronic assemblies was replaced. The pad will be reopened for
          normal work tomorrow morning.  Ordnance installation and checks
          of firing circuits are planned Thursday and closeouts of the aft
          compartment are scheduled when the pad is open.

               Launch of Mission STS-32 is targeted for Dec. 18 at 7:31
          p.m. EST.

                       STS-36 - ATLANTIS (OV 104) - OPF BAY 1

               Today, workers are preparing to install the right orbital
          maneuvering system pod. The pod is scheduled to be delivered to
          the OPF by noon today and installation will begin later tonight.
          Installation of the three main engines is planned for Friday and
          Saturday.

                      STS-33 - DISCOVERY (OV 103) - OPF  BAY 2

               Power up post-flight systems testing and inspections are
          scheduled this week. Heat shields have been removed in
          preparation for engine removal this week.

                         STS-36 SOLID ROCKET BOOSTERS - VAB

               Stacking operations are continuing. The right forward center
          segment is scheduled to be stacked today.  Joint closeouts are
          underway. The external tank is scheduled to be mated to the
          boosters next week.