[sci.space.shuttle] Shuttle Status for 01/31/90

yee@trident.arc.nasa.gov (Peter E. Yee) (02/01/90)

                KSC SHUTTLE STATUS REPORT - WEDNESDAY, JAN. 31, 1990

                    STS-36 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Loading of the hypergolic propellants into the orbiter's on-
          board storage tanks has been completed and the pad  is  scheduled
          to  be reopened for normal work at about noon today.   This morn-
          ing,  the solid rocket booster's hydraulic power units were  suc-
          cessfully hot fired for about 20 seconds.

               Technicians  will  begin  removing  heat shields and carrier
          panels from around  the  number  3  main  engine  today.  Shuttle
          program  managers  have decided to replace the high pressure fuel
          turbopump with a spare here at KSC.  Recent tests at the manufac-
          turer  revealed  minute  imperfections in a titanium inlet on the
          fuel pump.  X-rays of the fuel pumps and documentation papers are
          being  analyzed.  The reviews indicate one of Atlantis' pumps had
          weld flaws which are large enough to warrant repair. However, en-
          gineers have not been able to establish  definitely from  records
          whether the repairs were performed or not.

               The  Terminal  Countdown  Demonstration Test with the STS-36
          flight crew is set for Feb. 2-3.  The count is scheduled to begin
          at 8 a.m. EST Friday and the T zero is planned for 11 a.m. Satur-
          day.  The  STS-36  flight  crew  is scheduled to arrive at KSC on
          Thursday afternoon to participate in this pre-launch test.


                       STS-32 - COLUMBIA (OV 102) - OPF BAY 1

               The Long Duration Exposure Facility was hoisted out  of  the
          payload bay at about 7:45 p.m.  yesterday and placed in a special
          canister.  The canister left the Orbiter Processing  Facility  at
          about  3:45  a.m.  today for the Operations and Checkout Building
          and was moved into the high bay at noon.  Tomorrow, the LDEF will
          be removed from the canister and placed in a special  transporter
          for transfer to the  Spacecraft  and  Encapsulation  Facility  II
          where it will undergo post-flight analysis.

               Workers  are  preparing  to  remove the protective tail cone
          from the orbiter  and  will  begin  post-flight  inspections  and
          tests.


                       STS-31 - DISCOVERY (OV 103) - OPF BAY 2

               Activities  planned  this  week  include leak and functional
          checks of the three main engines and servicing  the  water  spray
          boilers with hydraulic fluid. Interface verification tests of or-
          biter  to payload connections are continuing this week.  A flight
          readiness test of the three main engines is  planned  this  week.
          This test exercises the engines' hydraulically driven valves.


                       STS-31 SOLID ROCKET BOOSTERS - VAB/RPSF

               The  new STS-31 aft booster,  previously designated for STS-
          35, is being prepared for stacking in the Rotation Processing and
          Surge Facility. This week, the upper and diagonal struts,  cables
          and  the  aft integrated electronics assembly are scheduled to be
          installed.  Meanwhile, closeouts of the left booster are underway
          in the VAB.


                       STS-31 SOLID ROCKET BOOSTERS - VAB/RPSF


               The  new STS-31 aft booster,  previously designated for STS-
          35, is being prepared for stacking in the Rotation Processing and
          Surge Facility. This week, the upper and diagonal struts,  cables
          and  the  aft integrated electronics assembly are scheduled to be
          installed.  Meanwhile, closeouts of the left booster are underway
          in the VAB.


                         STS-35 SOLID ROCKET BOOSTERS - VAB


               The left aft booster is now in the VAB transfer aisle  being
          prepared for stacking on mobile launcher platform 3.