[sci.space.shuttle] Shuttle Status for 03/02/90

yee@trident.arc.nasa.gov (Peter E. Yee) (03/06/90)

                KSC SHUTTLE STATUS REPORT - FRIDAY, MAR. 2 - 12:30 PM


                       STS-31 - DISCOVERY (OV 103) - OPF BAY 2

               Preparations are underway to  roll  Discovery  over  to  the
          Vehicle Assembly Building on Monday about 9-10 a.m.  Today, tech-
          nicians are finishing the weight and center of gravity checks and
          are scheduled to attach the  orbiter  to  its  transporter.  This
          weekend,  workers  will  finish  thermal protection system opera-
          tions, complete close outs of the elevons and conduct leak checks
          of that area for flight.

               While in the VAB,  Discovery will be mated to  the  external
          tank and solid rocket boosters and a test of the critical connec-
          tions  will be conducted.  Rollout to Launch Pad 39-B is targeted
          for March 16.  The Hubble Space  Telescope  is  scheduled  to  be
          transferred  to  the pad on March 26 and installed in Discovery's
          payload bay on the 28th.


                       STS-35 - COLUMBIA (OV 102) - OPF BAY 2

               Orbiter systems testing is continuing  to  prepare  Columbia
          for  the  upcoming  STS-35  mission in May.  Operations scheduled
          today include servicing the orbiter with potable water,  leak and
          functional testing of the water spray boilers, leak checks of the
          elevon cove area, and checks of the main propulsion system.

               The Astro payload is scheduled to be installed in Columbia's
          payload bay the middle of the month.


                    STS-36 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               The  mobile launcher platform is scheduled to be transferred
          to the refurbishment site near the VAB next week.

               The solid rocket boosters  arrived  at  Hangar  AF  on  Cape
          Canaveral Air Force Station yesterday and will be disassembled in
          the  next two weeks.  The motor cases will be returned to Thiokol
          for refurbishment.  The aft skirts and frustums  will  be  refur-
          bished at the USBI plant here at KSC.