[sci.space.shuttle] LH2 leak investigation

yee@trident.arc.nasa.gov (Peter E. Yee) (07/03/90)

Mark Hess
Headquarters, Washington, D.C.                       July 2, 1990
(Phone:  202/453-4164)

                     LH2 LEAK INVESTIGATION

History

     During the launch attempt for the STS-35 mission on May 29, 
1990, a hydrogen leak, in excess of limits established to 
maintain safe operating conditions, was detected by onboard 
hazardous gas detection systems.  Leakage was detected both in 
the aft compartment and external to the liquid hydrogen external 
tank/orbiter umbilical assembly.  

     A subsequent tanking test, that incorporated special ground 
instrumentation, further isolated the leak to the free space 
between the two halves of the umbilical assembly.  The umbilical 
provides capability to load propellant into the external tank and 
transfer propellant from the external tank to the Space Shuttle 
main engines during launch.  The umbilical disconnect assembly is 
the separation point between the orbiter and the external tank 
after main engine cutoff.  

     The design of the umbilical disconnect has remained the same 
throughout the Shuttle flight program except that a safety 
modification to incorporate a valve latch, which precludes 
inadvertent closure, was authorized after the Challenger 
accident.  Data from the tanking test determined that the design 
changes incorporated by this modification did not contribute to 
the leakage.

     Following rollback and orbiter demate, the LH2 External Tank 
(ET) side of the umbilical was removed and tested at Rockwell 
International, Downey, Calif.  The testing was performed under 
precisely controlled liquid hydrogen test conditions.  No leaks 
were detected.

     On June 29, 1990, NASA conducted a modified propellant 
loading test of the STS-38 Space Shuttle vehicle to ensure the 
safety and integrity of the orbiter/ET umbilical.  The test 
revealed a hydrogen leak.  The results indicate the leak is in 
the vicinity of the umbilical mating plates.  It appears to be 
primarily from the 17-inch line but possibly with a contribution 
from the 4-inch line.  The leak is flow rate and temperature 
dependent.  It is not as high as STS-35 but it exhibits many of 
the same characteristics.  

Current Status

     An extensive investigation is being performed to isolate the 
source of the leakage observed on both the STS-35 and STS-38 
vehicles.  

     Columbia is in the Orbiter Processing Facility (OPF).  The 
orbiter side of the LH2 umbilical from Columbia was shipped to 
Rockwell-Downey on Saturday and is being installed in a test 
stand which can test the orbiter and ET umbilicals in a mated 
configuration.  Engineers expect to begin cryogenic hydrogen 
testing of the umbilical on Thursday to further isolate the 
source of the leak.  

     In the interest of safety, all potential leak sources, 
including the very low probability of a parent metal flaw, are 
being investigated.  A detailed investigation of all aspects of 
the STS-35 and STS-38 component history, including acceptance 
test procedure requirements and data, and design changes being 
performed.  

     Processing of the STS-38 vehicle has been suspended.  
Engineers are continuing troubleshooting efforts on the Shuttle 
vehicle at Launch Pad 39-A.  Today, the external tank will be 
pressurized and leak checks conducted in the area of the orbiter-
to-external tank umbilical.  Another special tanking test is 
being considered using special leak detection sensors to help 
pinpoint the leak's location.


Program Team

     Leonard Nicholson, Deputy Director, Space Shuttle Program, 
will lead the NASA/industry team charged with analyzing the cause 
of the leak and determining corrective actions.

     Under Nicholson, four work teams have been formed:

     - Design and Analysis Team - to assess the flight hardware 
and ground support equipment hardware designs, fabrication and 
test programs, and assess ground processing procedures to ensure 
compliance with design intent.

     - Hardware Processing Team - to review all Kennedy Space 
Center procedures associated with the ET and orbiter processing, 
including "as run" data, problem reports, processes, procedures 
and personnel certification.

     - Data Analysis Team - to analyze data from the tanking 
tests and applicable launches to identify trends, define 
additional tests and instrumentation needed to understand and 
isolate the source of the leak and review all tests currently 
planned for completeness and appropriateness.

     - Fault Tree/Test Requirements Team - to develop and provide 
to the other teams a fault tree identifying failure scenarios, 
and identify additional tests and data requirements.

     An independent team, headed by Wayne Littles, Deputy 
Director of Marshall Space Flight Center, Huntsville, Ala., also 
has been formed with senior NASA and contractor representatives 
who are experts in liquid hydrogen technology.  While they will 
work independently of the investigation teams, they will report 
to Nicholson, and support the team, as appropriate.


Acceptance Test Procedure (ATP)

     The ET/Orbiter umbilical is fully developed and qualified 
flight hardware that has met all of the functional requirements 
stipulated by specification.  

     An acceptance test procedure, which is a screen to verify 
the manufacturing process for each component delivered, has been 
developed from performance requirements.  The ATP stipulates the 
use of liquid nitrogen as an acceptable substitute for liquid 
hydrogen, which is extremely dangerous and volatile to handle.  

     The disconnect component specification allows a maximum 
hydrogen leakage of 200 standard cubic inches per minute (scim) 
for the mated disconnect assembly at cryogenic temperature (150 
scim for the ET and 50 scim for the orbiter).  The ATP has a more 
stringent limit on the ET disconnect, which is 50 scims.  This 
allowable leakage rate was established to compensate for the 
temperature and media differences between liquid nitrogen and 
liquid hydrogen.  The orbiter disconnect underwent ATP testing 
with liquid hydrogen because there are a limited number of 
production units.


Future Steps

     Until the leak investigation is completed, Shuttle flights 
have been suspended.  Returning the Shuttle fleet to flight 
status is the highest priority in the Space Flight Office, and 
every available resource within the Shuttle program is being 
brought to bear on solving this problem.  NASA is confident that 
the source of the leak can be isolated quickly and the problem 
fixed with minimum disruption to the Shuttle flight program.

     Independent of these events, a component redesign to replace 
the current umbilical disconnect with a new design has been 
underway and is well into the preliminary design phase.  The new 
disconnect incorporates significant safety improvements, 
including redundant seals at all locations.