[sci.space.shuttle] Shuttle Status for 07/05/90

yee@trident.arc.nasa.gov (Peter E. Yee) (07/06/90)

                 KSC SHUTTLE STATUS - THURSDAY JULY 5, 1990  11 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A


               Today,  a liquid leak check of auxiliary power units 1 and 2
          are planned to verify there are no internal seal leaks. Engineers
          are putting requirements together for another tanking test at the
          pad  as troubleshooting of the hydrogen leak continues.  The test
          will likely occur mid-next week. Meanwhile,  tests are planned to
          obtain  additional signatures from the two leak detectors mounted
          exterior of the orbiter-to-external  tank  disconnect.  The  con-
          figuration of the vehicle will be maintained until further direc-
          tion from the team investigating the leak.

                       STS-35 - COLUMBIA (OV 102) - OPF BAY 2

               The  new  17-inch  disconnect from the Shuttle Endeavour was
          installed on Columbia Tuesday  evening  and  closeout  operations
          such  as foaming around the disconnect are underway.  Leak checks
          are planned.   A cold flow test of the two disconnects and  seals
          used  in the STS-35 tanking test is planned late Friday or Satur-
          day at the Rockwell plant in Downey, Calif.


                       STS-41 - DISCOVERY (OV 103) - OPF BAY 1

               All three shuttle  main  engines  have  been  installed  and
          hookups  and  leak  checks  are underway.  Repairs to Discovery's
          right payload bay door are continuing.  Tests  of  the  orbiter's
          systems  are  continuing today.  Thermal protection system opera-
          tions are underway on all areas of the vehicle.

               Tests are continuing on the two orbital  maneuvering  system
          pods at the Hypergolic Maintenance Facility.  About 50 tiles were
          removed from the right pod  after  a  small  oxidizer  leak  last
          month.  Replacement  of  the  tiles  is underway in parallel with
          other testing. Discovery is being prepared for the STS-41/Ulysses
          flight, scheduled for launch in October.

                         STS-41 SOLID ROCKET BOOSTERS - VAB

               The right forward center segment is being transferred to the
          Vehicle Assembly Building today for mate to the stack in the next
          few days. Closeout operations of the boosters are scheduled.