[sci.space.shuttle] Shuttle Status for 07/10/90

yee@trident.arc.nasa.gov (Peter E. Yee) (07/16/90)

                 KSC SHUTTLE STATUS - TUESDAY JULY 10, 1990  10 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Technicians are continuing to set up special instrumentation
          for the liquid hydrogen tanking test now planned on Friday.  This
          test  will  be another attempt to isolate the source of the leak.
          Today,  special baggies are being installed around the 17  and  4
          inch disconnects in an effort to contain leaks during the test.

               The  call-to-stations  for  the  test is scheduled at 7 a.m.
          Thursday and the Rotating Service Structure will  be  moved  away
          from the vehicle at 11 p.m.  that night.  Chilldown of the liquid
          hydrogen lines is set for 7 a.m.  Friday with slow fill occurring
          shortly afterwards.

                       STS-35 - COLUMBIA (OV 102) - OPF BAY 2

               Pneumatic leak checks of the newly installed 17-inch discon-
          nect were successfully completed.  Measurements of the disconnect
          are planned tomorrow by the vendor.

               Tests of the two 17-inch disconnects and seals used  in  the
          STS-35  tanking  test  were  conducted  at  the Rockwell plant in
          Downey, Calif. Data analysis is continuing. Meanwhile, the 4-inch
          recirculation line on the STS-35 tank will be replaced  tomorrow.
          After  several tanking operations,  the integrity of the exterior
          thermal foam on the line was suspect.   The concern is that  some
          of  the foam could break away at liftoff and damage the orbiter's
          tiles.

                       STS-41 - DISCOVERY (OV 103) - OPF BAY 1

               The right hand radiator and auxiliary power  unit  number  3
          were installed yesterday. Tests of the orbiter's systems are con-
          tinuing today.  Thermal protection system operations are underway
          on all areas of the vehicle.

               Tests are continuing on the two orbital  maneuvering  system
          pods  and forward reaction control system at the Hypergolic Main-
          tenance Facility.   Discovery is  being  prepared  for  the  STS-
          41/Ulysses flight, scheduled for launch in October.

                         STS-41 SOLID ROCKET BOOSTERS - VAB

               Stacking  of  the  right  forward segment is underway today.
          Closeout operations of the boosters are scheduled.