[sci.space.shuttle] Space Shuttle Endeavour powered-on

yee@trident.arc.nasa.gov (Peter E. Yee) (07/16/90)

Mark Hess/Ed Campion                             July 6, 1990
Headquarters, Washington, D.C.
(Phone:  202/453-8536)

Kyle Herring
Johnson Space Center, Houston
(Phone:  713/483-5111)


RELEASE:  90-95

SPACE SHUTTLE ENDEAVOUR POWERED-ON


     The new Space Shuttle Endeavour was powered-on for the first 
time today at Rockwell International Corp.'s Orbiter Assembly 
Facility in Palmdale, Calif., 10 days ahead of schedule.  The 
event is a major milestone in the vehicle's construction 
signifying the initial flow of power to Endeavour's on-board 
electrical systems.

     The start of power-on testing marks the beginning of an 
eight-month test period for Endeavour, the fifth operational 
orbiter built by Rockwell's Space Systems Division (SSD) for 
NASA's Space Shuttle program.  During the next three months, 
Endeavour's on-board electrical systems will be functionally 
energized to verify that the vehicle's instrumentation is 
operational and that vehicle systems are performing to 
engineering specifications.

     Following completion of the power-on tests, a final 
acceptance test will be conducted to verify the performance of 
the total integrated vehicle.  Endeavour is scheduled for rollout 
and delivery to NASA in April 1991 and a first flight in early 
1992.

     In addition to the power-on tests, work continues on other 
elements of the vehicle.  Technicians are currently performing 
final structural mate of the wings to the aft fuselage.  
Installation of a drag chute assembly that will aid in vehicle 
deceleration and reduce loads on the landing gear and brakes is 
in progress.  Thermal protection system tile and blanket 
installations are ahead of schedule and approximately 75-80 
percent complete.  Aft fuselage system installations are 
continuing.

     Major structural components remaining to be mated to the 
vehicle include its body flap in July; vertical stabilizer, 
payload pay doors, and elevons in August; and forward reaction 
control system module in November.  Endeavour's orbital 
maneuvering system pods will be installed at Kennedy Space 
Center, Fla.

     Rockwell received authority to proceed with construction of 
Endeavour from NASA in August 1987, although production of many 
of the basic elements necessary for the vehicle was begun in 
1983, when NASA awarded Rockwell a contract to build orbiter 
spare parts.  Rockwell SSD manages the Endeavour construction 
program under the direction of NASA's Johnson Space Center, 
Houston.