[sci.space.shuttle] Shuttle Status for 07/20/90

yee@trident.arc.nasa.gov (Peter E. Yee) (07/21/90)

                 KSC SHUTTLE STATUS - FRIDAY JULY 20, 1990  10 a.m.


                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Today, the 48 bolts around the external tank liquid hydrogen
          flange will be over torqued by 10 percent in an  effort  to  stop
          the  leak  discovered  during last week's tanking test.  The bolt
          torquing activities were not worked last night as planned because
          of measurements taken yesterday.  Measurements taken of the  bolt
          flatness  and  gap distance did not give the expected results and
          mold impressions were made of each bolt.  It has been  determined
          that all bolts are within specifications.

               Yesterday,  no  leakage was detected while the external tank
          was pressurized to check for leaks at the flange and around  each
          bolt.

               Later  today,  the  primer  around  the flange welds will be
          removed and a check of the  integrity  of  the  flange  welds  is
          planned using a dye penetrant test that will reveal imperfections
          in  the  welds.  Workers at KSC are preparing for another tanking
          test next Wednesday, July 25.

               In parallel with the tank operation,  the number 3 auxiliary
          power unit was disconnected this morning. Replacement of the unit
          is underway today.  Tomorrow, the pad will be cleared for about 2
          shifts of all non-essential personnel while the new APU  is  con-
          nected.  On Sunday, work will center on preparing the vehicle for
          Wednesday's  test,  including  installation  of baggies and sense
          lines and foaming various areas.

                       STS-35 - COLUMBIA (OV 102) - OPF BAY 2

               Operations to install the 17-inch disconnect  into  Columbia
          are  continuing  today.  Parker Hannifan representatives are here
          today to perform tests of the new  disconnect. Yesterday, workers
          cleaned up hydraulic fluid that dripped from a  quick  disconnect
          onto the right inboard elevon flipper doors.  It is now estimated
          that about three ounces of fluid leaked out.

                       STS-41 - DISCOVERY (OV 103) - OPF BAY 1

               The left orbital maneuvering system pod is scheduled  to  be
          installed tomorrow. Engineers are evaluating one of the uppermost
          aft  fittings on the pod.   Checks of the RTG system are continu-
          ing.  Thermal protection system operations are  underway  on  all
          areas  of  the  vehicle.  Pre-flight  tests are continuing on the
          other systems.

               Leak tests and thruster replacements are continuing  on  the
          right orbital maneuvering system pod and forward reaction control
          system (FRCS) at the Hypergolic Maintenance Facility. The FRCS is
          scheduled to be delivered to the OPF tomorrow for installation on
          Monday.

               Work  is  underway to prepare a thruster for installation of
          the right OMS pod. The original thruster was damaged on Wednesday
          when it fell from a work stand at the HMF.  A leaking dynatube in
          the thruster was being inspected in the work stand. An evaluation
          of  the  damaged thruster is underway to determine if repairs can
          be made.  Discovery is  being  prepared  for  the  STS-41/Ulysses
          flight, scheduled for launch in October.



                         STS-41 SOLID ROCKET BOOSTERS - VAB

               Closeout   operations  are  underway  on  the  solid  rocket
          boosters.