[sci.space.shuttle] Shuttle Status for 07/26/90

yee@trident.arc.nasa.gov (Peter E. Yee) (07/27/90)

               Thursday July 26, 1990                      10:00 p.m.

                     KSC Space Shuttle Processing Status Report

          -----------------------------------------------------------------

                  STS-38  --  Atlantis (OV 104)  -  Launch Pad 39-A

               Following yesterday's liquid hydrogen tanking test on the
          shuttle Atlantis, shuttle project managers have decided to remove
          Atlantis from the pad and roll it back to the VAB for repairs.
          Results of yesterday's test confirmed the existence of a leak in
          the 17-inch umbilical flange joint on the external tank. Managers
          have said the space shuttle Columbia will fly next on mission
          STS-35.

               Two rollback scenarios are currently being discussed for
          Atlantis. The preferred involves not moving Atlantis until the
          day before Columbia is ready to roll out to pad A, probably near
          the end of the first week in August. The second scenario involves
          the possible effects of tropical storm Arthur, currently working
          its way northwest from the Caribbean. If Arthur is predicted to
          affect weather conditions at KSC, Atlantis may be moved as early
          as the first of next week.

               Boil off of the liquid hydrogen remnants in the external
          tank from yesterday's test was completed at 5:00 a.m. this
          morning. Post tanking test operations are in work and the
          rotating service structure is scheduled to be moved back around
          the orbiter by 11:00 a.m. Access to the orbiter's aft compartment
          is scheduled for 8:00 p.m. tonight.

               Engineers decided yesterday not to perform the APU hot fire
          as scheduled. Preparations are underway today to remove APU
          number three on Saturday.


                     STS-35  --  Columbia (OV 102)  -  OPF Bay 2

               Work continues today on the final testing of the 17-inch
          liquid hydrogen disconnect. Engineers need to perform a final
          flatness test before giving the final approval for flight.

               Leak checks are continuing on the GOX flow control valve and
          technicians are working on the high point bleed quick disconnect.
          Columbia is expected to be ready for rollover to the VAB for
          mating with the external tank and solid rocket boosters early
          next week.

               Columbia with the ASTRO-1 payload is now scheduled for
          flight in early September.


                     STS-41 -- Discovery (OV 103)  -  OPF Bay 1

               Preparations for the installation of Discovery's forward
          reaction control system are complete. Repairs on the left hand
          OMS pod thermal barrier are continuing. The right hand OMS pod
          interface operations are scheduled for today. Also in work today
          are water spray boiler operations, the hydraulic lifting of the
          number one Shuttle main engine dome and the RTG contingency
          platform fit checks.

               Discovery's next mission is Ulysses. Launch of STS-41
          remains on scheduled for October 5, 1990, from pad 39-B.