[sci.space.shuttle] Shuttle Status for 07/31/90

yee@trident.arc.nasa.gov (Peter E. Yee) (08/01/90)

                Tuesday July 31, 1990                      10:00 a.m.

                     KSC Space Shuttle Processing Status Report

          -----------------------------------------------------------------

                     STS-35  --  Columbia (OV 102)  -  OPF Bay 2

               Rollover of the orbiter Columbia to the Vehicle Assembly
          Building is targeted for early Thursday morning. The special tool
          needed to perform final borescope measurements and inspections on
          the external tank 17-inch disconnect has arrived. These
          procedures are currently underway as eleventh hour preparations
          for the move to the VAB continue.

               The crew hatch was closed yesterday and the strongbacks have
          been taken off the payload bay doors. Today, workers will install
          the aft compartment doors and transfer the orbiter transporter to
          the Orbiter Processing Facility for mating operations with
          Columbia.


                  STS-38  --  Atlantis (OV 104)  -  Launch Pad 39-A

               Post tanking operations continue at Pad A and preparations
          for hypergolic deservicing of the OMS/RCS system are currently
          underway. Call to stations for the operation is set for 4:00 p.m.
          today and the pad will be cleared beginning at mid-night tonight.
          Hypergolic deservicing is expected to take approximately 24 hours
          to complete. Meanwhile, engineers continue their preparations to
          remove APU number three. Removal of the auxiliary power unit is
          scheduled for Thursday.

               Rollback of Atlantis to the Vehicle Assembly Building is
          based on Columbia's readiness for rollout to pad A. Rollback is
          currently targeted for Wednesday August 8.


                     STS-41 -- Discovery (OV 103)  -  OPF Bay 1

               Yesterday, the OMS/RCS redundant electrical circuit
          verification tests were conducted. Work scheduled for today
          includes the right hand OMS pod interface verification test,
          water spray boiler servicing, and main propulsion system decay
          checks.
                         STS-41 -- ET/SRB  -  VAB High Bay 1

               Movement of the external tank from the storage cell in the
          Vehicle Assembly Building onto the transporter is in work today
          and preparations are underway to mate the tank with the solid
          rocket boosters tonight.

mmachlis@athena.mit.edu (Matthew A Machlis) (08/01/90)

I don`t suppose there`s any way we could get updates on what
exactly is going on with Endeavor as well...?

--
----------------------------------------------------------------------------
Matt Machlis
MIT Space Systems Laboratory
(617)253-2272