[sci.space.shuttle] Shuttle Status for 08/02/90

yee@trident.arc.nasa.gov (Peter E. Yee) (08/03/90)

               Thursday August 2, 1990                      10:00 a.m.

                     KSC Space Shuttle Processing Status Report

          -----------------------------------------------------------------

                     STS-35  --  Columbia (OV 102)  -  OPF Bay 2

               Rollover of the orbiter Columbia from the Orbiter Processing
          Facility to the Vehicle Assembly Building is currently assessed
          to be no earlier than mid-afternoon today. Crews are raising the
          landing gear this morning and positioning the orbiter transporter
          under the orbiter for the quarter mile move to the VAB. Final 17-
          inch seal installation has been delayed and work will be
          performed in the VAB transfer aisle prior to operations to mate
          the orbiter with the external tank and solid rocket boosters.
          Rollout to pad A is currently targeted for mid-next week.

                  STS-38  --  Atlantis (OV 104)  -  Launch Pad 39-A

               Hypergolic deservicing of Atlantis' OMS/RCS systems at pad A
          has been completed and the pad is open for routine work. Today,
          mapping and baggie removal on the liquid hydrogen lines will be
          performed and auxiliary power unit number three will be removed
          from Atlantis' aft compartment.

               Rollback of Atlantis to the VAB is based on Columbia's
          readiness for rollout to pad A. Current plans call for Atlantis
          to rollback to the VAB August 8 and wait outside high bay 1 until
          Columbia rolls past it out of high bay 3 the following day,
          August 9. Once Columbia is at pad A, Atlantis will be moved into
          bay three for destack operations.

                     STS-41 -- Discovery (OV 103)  -  OPF Bay 1

               The left hand OMS pod is in place on the orbiter and the
          attach bolts are being torqued this morning. Integration and
          verification tests are in work today on both the left and right
          hand pods. The external tank functional test was performed
          successfully yesterday and hypergolic operations are scheduled
          for Saturday for the installation of APU number two.

               In Discovery's payload bay late Tuesday night as work was
          underway to close the payload bay doors for tile work, a worker
          discovered that the leg of a step down platform was resting
          against a portion of freon coolant loop number two, creating a
          crimp in the 3/4 inch stainless steal line.

               X-rays and mold impressions of the 1/4 inch by 1/4 inch dent
          were sent to the Rockwell plant in Downey, Ca., to determine the
          exact nature and extent of the crimp. Managers hope to be able to
          fly Discovery as is. However, if work is required to repair the
          line, it could impact Discovery's rollover date by two to three
          days. Rollover to the VAB is currently targeted for August 18.


                         STS-41 -- ET/SRB  -  VAB High Bay 1


               Lifting of the external tank for mating with the solid
          rocket boosters took place yesterday with soft mate occurring at
          3:30 p.m.