[sci.space.shuttle] Shuttle Status for 08/06/90

yee@trident.arc.nasa.gov (Peter E. Yee) (08/07/90)

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          Monday, August 6                                  10:30 a.m. EDT

                   STS-35  --  Columbia (OV-102) -- VAB High Bay 2

               Operations to mate Columbia with  the  external  tank    are
          still underway.  At present, the Call to Stations for the Shuttle
          Interface Test,  which checks out electrical and mechanical  con-
          nections between the orbiter and the tank, is targeted for mid to
          late first shift on Tuesday.  Rollout to Launch Pad 39A will move
          to Friday,  with exact time to be determined.  Managers are  cur-
          rently  assessing  the  practability of moving some portions of a
          series of routine interface testing to the pad.
               Over the weekend,  engineers resolved a problem with the in-
          stallation  of an electrical monoball assembly.  That assembly is
          currently being installed.  Other engineering evaluation included
          the assessment of work items such as a too-short "power" bolt.
                The  launch  of STS-35 and the Astro-1 observatory is still
          scheduled for early September.  The next payload operations,  in-
          cluding  servicing of the Broad Band X-Ray Telescope,  have moved
          to Saturday.  The BBXRT frozen argon servicing performed prior to
          rollover from the OPF will provide cooling through Aug. 13.

                        STS-41 -- Discovery (OV-103) -- OPF Bay 1

               Technicians  have completed cabin leak checks.  Installation
          of an auxiliary power unit began this weekend.  Later this  week,
          fuel  line  connections and leak checks will be performed as part
          of this operations.
               Radiator  work  on  the  forward  right-hand  aft  door   is
          scheduled to begin tomorrow morning. The orbiter purge, vent, and
          drain door functional test has been completed. Water spray boiler
          servicing  is scheduled.  OMS/RCS aft pod mating and testing con-
          tinues.  Scheduled portions of ordnance  installation  have  been
          completed.


                      STS-38 --  Atlantis (OV-104) -- Launch Pad 39A

               Based  on  Columbia's  projected  Friday rollout,  Atlantis'
          rollback to the VAB will be rescheduled for 12:01 a.m.  Thursday,
          August 9.    Atlantis will be moved to outside High Bay 1,  until
          Columbia is rolled out the next day. Then, Atlantis will be moved
          into the VAB, destacked, and returned to the OPF.
               At the pad,  vehicle power is scheduled to come up on second
          shift.  Payload  bay door operations are in work,  with the doors
          scheduled to close later today.

          For more information on KSC's Shuttle Processing Status,  contact
          Patricia Phillips at 407-867-2468.