[sci.space.shuttle] Shuttle Status for 08/13/90

yee@trident.arc.nasa.gov (Peter E. Yee) (08/14/90)

            KSC SHUTTLE STATUS REPORT - MONDAY, AUGUST 13, 1990  11 A.M.

                        STS-35 - COLUMBIA (OV 102) - PAD 39-A

               The Shuttle Interface Test, which began early Saturday morn-
          ing, will continue through tomorrow.  Launch pad  validations  are
          also  scheduled to continue through tomorrow.  A leak test,  with
          gaseous helium, of the external tank flange this weekend revealed
          some leakage,  however,  engineers have determined it  is  within
          specifications.

               Servicing  of  the Broad Band X-ray Telescope with argon was
          completed on Saturday.  Gaseous oxygen flow control  valves  were
          installed in the vehicle's main propulsion system this weekend.

               Routine  tests  of the main propulsion system are continuing
          this week.  Preparations are underway to conduct a helium  signa-
          ture leak check of the three main engines on Thursday.

               The Flight Readiness Review,  where shuttle managers set the
          official launch date, is scheduled for Aug. 20-21 here at Kennedy
          Space Center.

                     STS-38 - ATLANTIS (OV 104) - VAB HIGH BAY 3

               Operations to demate the shuttle Atlantis from the  external
          tank  began this weekend but were temporarily halted this morning
          when a valve in the VAB firex system failed causing water to drip
          onto power transformers.  The power in VAB high bay  3  has  been
          cut  off  to avoid electrical shorts.  The water has been cleaned
          up. Officials are determining if that part of the firex system is
          necessary to continue with demate operations.  There was no water
          on flight hardware.

               Atlantis will be towed to the OPF after demate where work to
          ready it for the STS-38 mission will commence including replacing
          seals  in  the  17-inch  disconnect  assembly  and for repairs to
          tiles.

                       STS-41 - DISCOVERY (OV 103) - OPF BAY 1

               The freon cooling system was serviced this weekend and  sam-
          pling and adjusting is planned  in the next few days. The payload
          bay  doors  were closed for thermal protection system operations.
          Closeouts are underway on all areas of the  vehicle.  Pyrotechnic
          devices  for  the  robot arm and the RTG system will be installed
          after the RTG system is serviced with water.  The date of Aug. 18
          for rolling the vehicle over to the VAB is being  evaluated.  The
          routine rollover review meeting will be held Friday.

daveb@athena.mit.edu (Dave Balkwill) (08/14/90)

In article <56012@ames.arc.nasa.gov> yee@trident.arc.nasa.gov (Peter E. Yee) writes:
>          also  scheduled to continue through tomorrow.  A leak test,  with
>          gaseous helium, of the external tank flange this weekend revealed
>          some leakage,  however,  engineers have determined it  is  within
>          specifications.

OK, I'll bite first.
Anybody know what the "specifications" are?
How stringent are they?
Presumably, they are well within "safe" bounds whatever that may be.

--
------  daveb@space.mit.edu  OR  wonko@athena.mit.edu  ---------
| "In Sweden, we play soccer in weather like this, in shorts." |
|    --  Bjorn Nittmo, kicker for NFL New York Giants          |
-----  DISCLAIMER:  Of course they're only my opinions! --------

simon@vision.UUCP (Simon Taylor) (08/15/90)

In article <56012@ames.arc.nasa.gov> yee@trident.arc.nasa.gov (Peter E. Yee) writes:
>          Closeouts are underway on all areas of the  vehicle.  Pyrotechnic
>          devices  for  the  robot arm and the RTG system will be installed
>          after the RTG system is serviced with water.  

	I am aware of Pyrotechnic devices being used on other parts of the
	Shuttle, but what are they used for on the robot arm ?


Simon Taylor
Support & Training Manager
VisionWare Ltd                  UUCP    : simon@vision.uucp
57 Cardigan Lane                BANGNET : ...!uunet!mcsun!ukc!vision!simon
Leeds                           PHONE   : +44 532 788858 Ext. 228
LS4 2LE                         FAX     : +44 532 304676
England                     
-------------------------------------------------------------------------------
---------------- VisionWare: The Home Of DOS-UNIX Integration -----------------
-------------------------------------------------------------------------------

pjs@aristotle.JPL.NASA.gov (Peter Scott) (08/16/90)

In article <1160@vision.UUCP>, simon@vision.UUCP (Simon Taylor) writes:
> In article <56012@ames.arc.nasa.gov> yee@trident.arc.nasa.gov (Peter
E. Yee) writes:
> >          Closeouts are underway on all areas of the  vehicle. 
Pyrotechnic
> >          devices  for  the  robot arm and the RTG system will be
installed
> >          after the RTG system is serviced with water.  
> 
> 	I am aware of Pyrotechnic devices being used on other parts of the
> 	Shuttle, but what are they used for on the robot arm ?

In the event that the robot arm goes out of control and starts heading
for a populated area, the RSO will destroy it to protect innocent
civilians.

Sorry, couldn't resist  :-)

--
This is news.  This is your       |    Peter Scott, NASA/JPL/Caltech
brain on news.  Any questions?    |    (pjs@aristotle.jpl.nasa.gov)

henry@zoo.toronto.edu (Henry Spencer) (08/16/90)

In article <1160@vision.UUCP> simon@vision.UUCP (Simon Taylor) writes:
>	I am aware of Pyrotechnic devices being used on other parts of the
>	Shuttle, but what are they used for on the robot arm ?

There is an emergency jettison system for the arm, in the event that it
locks up while in use and can't be stowed properly for reentry.
-- 
It is not possible to both understand  | Henry Spencer at U of Toronto Zoology
and appreciate Intel CPUs. -D.Wolfskill|  henry@zoo.toronto.edu   utzoo!henry