[sci.space.shuttle] Shuttle Status for 08/28/90

yee@scam.Berkeley.EDU (Peter Yee) (08/29/90)

            KSC SHUTTLE STATUS REPORT - TUESDAY, AUGUST 28 1990  11 A.M.

                        STS-35 - COLUMBIA (OV 102) - PAD 39-A

               Ordnance devices were installed on the vehicle  and  circuit
          resistance   checks   of   pyrotechnic  devices  were  conducted.
          Closeouts of the ordnance work is underway. Pressurization of the
          onboard hypergolic propellant tanks was also completed.   The pad
          was  reopened last night and technicians gained access to the aft
          compartment about 6 p.m. Closeouts of the aft compartment are un-
          derway. The flight doors are scheduled to be installed on the aft
          late tomorrow afternoon.

               A routine purge of the cavity between the orbiter and exter-
          nal tank liquid hydrogen 17-inch umbilical is scheduled today.

               Preparations are underway to service the  Broad  Band  X-Ray
          Telescope this evening.  This will be the last servicing prior to
          launch.

               Columbia and the Astro-1 payload are scheduled for launch on
          Sept. 1. The launch countdown is scheduled to begin at 1 a.m. EDT
          Wednesday, Aug.  29,  at the T minus 43 hour mark,  leading up to
          the planned liftoff at 1:17 a.m.  EDT on Saturday,  Sept.  1. The
          flight crew is scheduled to arrive at KSC tomorrow at  9:30  p.m.
          EDT.

               An  evaluation  of the countdown and launch schedule will be
          made   this afternoon to determine the  progress  of  Discovery's
          VAB processing and targeted pad rollout time.

                       STS-41 - DISCOVERY (OV 103) - OPF BAY 1

               Discovery  was  softmated  to the external tank at 3:54 a.m.
          today. Hard mate is targeted for this morning. Electrical connec-
          tions will  commence  today.  Power  up  testing  is  planned  on
          Thursday.   Some of the testing of those connections will be con-
          ducted after the vehicle arrives at Launch Pad 39-B.

               The  schedules  for  Discovery  and   Columbia   are   being
          evaluated, however, Discovery's rollout to the Launch Pad is tar-
          geted for Friday midnight.

                       STS-38 - ATLANTIS (OV 104) - OPF BAY 2

               Preparations  are underway to repair  the freon cooling sys-
          tem.  Checks of several leaking reaction control system thrusters
          are continuing.   Leak checks of the main propulsion system shaft
          seals have been completed.