[sci.space.shuttle] Shuttle Status for 09/10/90

yee@trident.arc.nasa.gov (Peter E. Yee) (09/11/90)

             KSC SHUTTLE STATUS REPORT - MONDAY, SEPT. 10, 1990 10:30 AM

                        STS-35 - COLUMBIA (OV 102) - PAD 39-A

               The new hydrogen recirculation pump  package  is  being  in-
          stalled  today  and leak checks are planned this afternoon.  Late
          tonight,  engineers will conduct a helium signature leak test  of
          the  liquid  hydrogen side of the main propulsion system and main
          engines.   Following the test,  technicians will refoam the  pump
          and connecting joints.

               No leaks were detected during tests of the pump package this
          weekend. The package  was removed Sunday and flown to the Johnson
          Space Center for analysis.

               Launch  of STS-35 is dependent on the successful replacement
          and retest of the recirculation pump package.  A  tentative  time
          frame for launch is the week of Sept. 17.

                       STS-41 - DISCOVERY (OV 103) - PAD 39-B

               Results  from  a pressurization test of the freon system are
          being analyzed.  This test is designed to verify  structural  in-
          tegrity  of  the system.  A leak was detected in the system after
          the vehicle was in the vertical positon.

               A helium signature leak test of the three main  engines  and
          main propulsion system was successfully completed overnight.

               The  Ulysses payload was installed in the payload bay Satur-
          day.  The interface verification test is  planned  Wednesday  and
          Thursday and the end-to-end test is set for Friday.

               The  Countdown  Demonstration  Test began on time today at 8
          a.m.  at the T-24 hour mark.  All countdown events will be  simu-
          lated  or abbreviated leading up to a main engine cutoff at about
          11 a.m. tomorrow.

               The STS-41 flight crew arrived  at KSC yesterday  for  emer-
          gency training and to participate in the routine test.

                       STS-38 - ATLANTIS (OV 104) - OPF BAY 2

               Operations  to  remove  and replace the flash evaporator are
          continuing.  The unit is scheduled to  be  removed  and  replaced
          today.

               Tile repairs are continuing and thermal control blankets are
          being installed on the forward bulkhead.

               Atlantis  is  being prepared for rollover to the VAB the end
          of the month.