[sci.space.shuttle] Shuttle Status for 09/26/90

yee@trident.arc.nasa.gov (Peter E. Yee) (09/27/90)

          KSC SHUTTLE STATUS REPORT - WEDNESDAY, SEPT. 26, 1990 11:30 AM


                       STS-41 - DISCOVERY (OV 103) - PAD 39-B

               The two space suits carried aboard Discovery for contingency
          purposes are being installed in the airlock today. Later today, a
          test to simulate launch day events for the Inertial  Upper  Stage
          will begin.  The test is planned to start at about 5 p.m. tonight
          and will end with a simulated T-0 at about 7:30 tomorrow morning.

               Tomorrow,  a purge of the external tank is planned  and  the
          freon system will be topped off for launch.

               On Friday,  hypergolic propellant tanks on board the orbiter
          will be pressurized and closed out,  and ordnance devices will be
          installed and firing circuits will be checked.

               Closeouts  of  the  orbiter's  aft compartment are underway.
          This work includes applying foam to various  areas  of  the  main
          propulsion system,  final inspections of various components, main
          engine closeouts, cleaning and removing platforms for flight. The
          aft is scheduled to be closed out for flight on Sunday.

               Discovery and the Ulysses spacecraft are being prepared  for
          an October 6 launch date. The launch countdown will begin at 3:30
          a.m.  EDT Wednesday, Oct. 3, at the T-43 hour mark, leading up to
          the liftoff at 7:35 a.m. EDT.



                        STS-35 - COLUMBIA (OV 102) - PAD 39-A

               Leak tests are continuing  on  the  main  propulsion  system
          valves,  actuators and areas of the recirculation pump package to
          try to isolate the source of the leak.  Nothing has been detected
          so  far.  The KSC team is working with the tiger team assigned to
          find the fuel leak.  The team is planning to leak test a prevalve
          for main engine 2 using dry ice to cool it down.  Out of over 200
          joints in the main propulsion system, the team has 83 joints that
          are possible contributors to the leakage.

               Details  and requirements are being identified for a tanking
          test next month.  A definite date for the test has not  yet  been
          set.


                       STS-38 - ATLANTIS (OV 104) - OPF BAY 2


               The  auxiliary  power  unit  was installed yesterday.  Tech-
          nicians are adjusting the amount of freon in cooling loop 2.  In-
          spections  of the radiator are continuing.  Seals for the 17 inch
          disconnect  assembly  are  scheduled  to  be  installed   Friday.
          Closeouts  are underway on all areas of the vehicle.  Atlantis is
          being prepared for rollover to the VAB at midnight Tuesday,  Oct.
          2.

               Closeouts of the  external tank are continuing in the VAB in
          preparation for orbiter mating operations scheduled next week.