[sci.space.shuttle] Shuttle Status for 10/26/90

yee@trident.arc.nasa.gov (Peter E. Yee) (10/27/90)

               Friday October 26, 1990                 11:00 a.m. EDT

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------

                      STS-38 -- Atlantis (OV-104)  -  Pad 39-A

               Operations were briefly halted at the pad this morning as
          SCAPE operations were instituted to repair minor leaks at the
          hypergolic oxidizer and fuel farms. The pad was re-opened for
          operations at 10:30 a.m. The leaks were thought to be as a result
          of cooler weather experienced overnight. No impact in the
          schedule is expected.

               Purge operations of the external tank have been completed
          following the successful tanking test Wednesday. Access was
          gained to the aft compartment and work continues to ready the
          vehicle for flight. At the pad today, fuel cell voltage
          adjustments will be made.

               This weekend, the mass memory unit on the orbiter will be
          changed out and the Shuttle main engine flight readiness test
          will be conducted. Monday, liquid oxygen tankers will arrive at
          the pad to replenish the on-site storage tanks.

               The Flight Readiness Review is scheduled for next Monday and
          Tuesday, following which an announcement is expected setting the
          launch date and launch period for Atlantis' Department of Defense
          mission.


                     STS-35  --  Columbia (OV 102)  -  Pad 39-B

               Foaming operations in the aft compartment have been
          completed as workers make last minute preparations to ready the
          Shuttle for the special tanking test early next week. The
          schedule indicates the test of the liquid hydrogen lines on
          Columbia will occur Tuesday, Oct. 30, with a slight possibility
          that the test may slip a day, depending on work to be performed
          this weekend.

               Today crews will install special cameras in the aft
          compartment for the tanking test. The cameras will allow
          engineers an opportunity to view the compartment where the liquid
          hydrogen lines are located and hopefully help isolate the exact
          location of the leaks. The two special aft compartment doors made
          of Lexan, a clear plexiglass-like material, have been installed.
          Final baggy leak checks will take place Monday.

               Payload servicing has been completed and the payload bay
          doors will be closed late this afternoon.


                     STS-39 -- Discovery (OV 103)  -  OPF Bay 1

               Power-on testing is scheduled to begin today, followed by
          hypergolic offload preparations. Hypergols are scheduled to be
          removed from the orbiter's OMS/RCS systems this weekend. The
          Forward Reaction Control System has been re-scheduled to be moved
          to the Hypergolic Maintenance Facility early next week.